Tesla Terafactory Texas Update #170 in 4K: Adding The Double Tees - 06/16/21 (5:00pm | 96°F)

-Hey guys, it’s Randy! Today’s video shows some major updates in the GigaPress area with Double Tees being installed as well as other general updates around the main site. I also make the trip across the highway to get an updated look at the progress taking place on that side.

Here are today’s key takeaways:
-The GigaPress area shows 2 horizontal cross beams installed and the first full row of Double Tees consisting of 7 sectional pieces have also been installed today! We can see several more sets of Double Tees in the area so there’s a strong likelihood these will be installed by end of day Thursday and this entire section for this type of work is definitely speeding along much faster than when we previously saw it on the site.
-On the east side of the BIW area near the GigaPress end, I captured this being delivered. Unfortunately, I couldn’t get much closer but this is about as close as I could zoom in on a still image and it actually looks like a module consisting of a robot in a box. Please leave a comment on what you guys think it could be or what it could possibly be a part of if you have any ideas.
-Further south, we get a better look at the area just east of where the Stamping and BIW buildings meet where a new road looks to be going in.
There looks to be work taking place in the detention pond furthest south and closest to the highway bridge where they are possibly regrading it since it is still in pretty rough shape after the string of storms we had not too long ago.
-Next, we see an updated progress shot of the structural steel getting closer to the angled corner.
-The underground stormwater detention system now shows concrete all over the place and the mud slab that was at the top right we saw yesterday now has a column formed and concrete poured on it. At the top center of the image, we see 4 new footings that were not present yesterday have also been dug and have the initial concrete pad poured in the center of them.
-Across the highway, we get a better look at the work being done on the road that will provide access to both sides. We also get a glimpse here of another neatly shaped detention pond by the looks of it. Closer to the bridge we see newly laid rolls of geotextile fabric extending the road directly underneath the lanes of the highway!
-The large hill excavation is still in progress and the tops of most of the hills have been scraped and flattened at this point.
-Finally, we wrap up looking back towards the main site and see that most of the activity around the large foundation that’s been prepped on this side looks to be done for the time being as they probably are concentrating on other areas of this side since the main work here looks finished.

If you’re new here, please be sure to like, subscribe, and hit the notification bell if you want to be kept up-to-date with the latest content. If you enjoy it, please consider supporting the channel on Patreon via the links in the description or at the end of the video.

--------------------------------------------

Affiliate Links for Equipment Used or Recommended:

DJI Mavic Air 2 Fly More Combo w/Smart Controller: https://amzn.to/3pqD794
DJI Mavic Mini 2 Fly More Combo: https://amzn.to/3rtdLJH
DJI Mavic Mini Fly More Combo: https://amzn.to/34NZgq0
SanDisk 128gb Micro SD Card: https://amzn.to/3pqEftk

--------------------------------------------
Support Me On Patreon or PayPal

https://www.patreon.com/terafactorytexas

https://paypal.me/davismediasolutions

--------------------------------------------

Tesla Referral Code

https://ts.la/randy95094

--------------------------------------------

Date Filmed: 06-16-21
Time of Day: Late Afternoon - 5:00pm

--------------------------------------------

Social Media

Twitter: https://twitter.com/Terafactorytx
Instagram: https://www.instagram.com/terafactorytx/

--------------------------------------------

Additional Terafactory Texas Footage Channels
NOTE: We all film at different times throughout the day so check us all out in order to catch footage from certain times of the day.

@JeffRoberts - https://www.youtube.com/user/peterdog15
@JoeTegtmeyer - https://www.youtube.com/c/JoeTegtmeyer
@TxTerafactory - https://www.youtube.com/c/TexasTerafactory

--------------------------------------------

Giga Berlin Footage

The Wolfpack Berlin: https://www.youtube.com/c/thewolfpackberlin

--------------------------------------------

Music

Turn Up Burn Up - Diamond Ortiz
Monument - TrackTribe
Orange - Topher Mohr and Alex Elena

Видео Tesla Terafactory Texas Update #170 in 4K: Adding The Double Tees - 06/16/21 (5:00pm | 96°F) канала Terafactory Texas
Показать
Комментарии отсутствуют
Введите заголовок:

Введите адрес ссылки:

Введите адрес видео с YouTube:

Зарегистрируйтесь или войдите с
Информация о видео
17 июня 2021 г. 18:31:38
00:20:32
Другие видео канала
Tesla Terafactory Texas Update #33 in 4K - 10/05/20 (Late Afternoon - 5:45pm)Tesla Terafactory Texas Update #33 in 4K - 10/05/20 (Late Afternoon - 5:45pm)Tesla Terafactory Texas Update #92 in 4K: Upon Further Review - 01/13/21 (5:00pm)Tesla Terafactory Texas Update #92 in 4K: Upon Further Review - 01/13/21 (5:00pm)Tesla Terafactory Texas Update #190 in 4K: Paving Resumes - 07/28/21 (5:00pm | 98°F)Tesla Terafactory Texas Update #190 in 4K: Paving Resumes - 07/28/21 (5:00pm | 98°F)Tesla Terafactory Texas Update #77 in 4K: Raising More Everything- 12/17/20 (5:00pm)Tesla Terafactory Texas Update #77 in 4K: Raising More Everything- 12/17/20 (5:00pm)Terafactory Texas Update #21 - 9/10/20 - Wet And Windy!!!Terafactory Texas Update #21 - 9/10/20 - Wet And Windy!!!Tesla Terafactory Texas Update #99 in 4K:  Late Evening Flyover - 01/26/21 (6:15pm)Tesla Terafactory Texas Update #99 in 4K: Late Evening Flyover - 01/26/21 (6:15pm)Tesla Terafactory Texas Update #213 in 4K: North End Roof Gaps Filled 09/17/21 (7:15pm | 91°F)Tesla Terafactory Texas Update #213 in 4K: North End Roof Gaps Filled 09/17/21 (7:15pm | 91°F)Tesla Terafactory Texas Update #65 in 4K: Structure Build Speed Increasing - 11/30/20 (5:15pm)Tesla Terafactory Texas Update #65 in 4K: Structure Build Speed Increasing - 11/30/20 (5:15pm)Terafactory Texas Update #30 - 9/29/20  ( Late Afternoon) - Major Work In The SouthTerafactory Texas Update #30 - 9/29/20 ( Late Afternoon) - Major Work In The SouthTesla Terafactory Texas Update #189 in 4K: Shaping Perimeter Roads & Lots - 07/27/21 (4:30pm | 98°F)Tesla Terafactory Texas Update #189 in 4K: Shaping Perimeter Roads & Lots - 07/27/21 (4:30pm | 98°F)Tesla Terafactory Texas Update #231 in 4K: Paving In Overdrive 12/01/21 (4:45pm | 76°F)Tesla Terafactory Texas Update #231 in 4K: Paving In Overdrive 12/01/21 (4:45pm | 76°F)Tesla Terafactory Texas Update #186 in 4K: Loading Docks or Charging Lot - 07/21/21 (5:00pm | 91°F)Tesla Terafactory Texas Update #186 in 4K: Loading Docks or Charging Lot - 07/21/21 (5:00pm | 91°F)Tesla Terafactory Texas Update #216 in 4K: Many Exterior Updates 09/23/21 (7:15pm | 80°F)Tesla Terafactory Texas Update #216 in 4K: Many Exterior Updates 09/23/21 (7:15pm | 80°F)Tesla Terafactory Texas Update #197 in 4K: Joining The SW East & West Sides 08/12/21 (5:30pm | 97°F)Tesla Terafactory Texas Update #197 in 4K: Joining The SW East & West Sides 08/12/21 (5:30pm | 97°F)Tesla Terafactory Texas Update #137: Amazing Battery Structure Progress - 04/12/21 (5:00pm | 89°F)Tesla Terafactory Texas Update #137: Amazing Battery Structure Progress - 04/12/21 (5:00pm | 89°F)Tesla Terafactory Texas Update #145 in 4K: Two For One - 04/28/21 (5:15pm | 82°F)Tesla Terafactory Texas Update #145 in 4K: Two For One - 04/28/21 (5:15pm | 82°F)Tesla Terafactory Texas Update #176 in 4K: Filling in the Gaps - 06/29/21 (5:30pm | 76°F)Tesla Terafactory Texas Update #176 in 4K: Filling in the Gaps - 06/29/21 (5:30pm | 76°F)Tesla Terafactory Texas Update #109 in 4K:  Back To Work - 02/22/21 (5:15pm | 73°F)Tesla Terafactory Texas Update #109 in 4K: Back To Work - 02/22/21 (5:15pm | 73°F)Tesla Terafactory Texas Update #81 in 4K: Starting On The Docks - 12/28/20 (5:00pm)Tesla Terafactory Texas Update #81 in 4K: Starting On The Docks - 12/28/20 (5:00pm)Tesla Terafactory Texas Update #93 in 4K: Casting & Stamping Foundation Progress - 01/14/21 (5:00pm)Tesla Terafactory Texas Update #93 in 4K: Casting & Stamping Foundation Progress - 01/14/21 (5:00pm)Tesla Terafactory Texas Update #91 in 4K: Cranes Doing Crane Things - 01/12/21 (5:00pm)Tesla Terafactory Texas Update #91 in 4K: Cranes Doing Crane Things - 01/12/21 (5:00pm)
Яндекс.Метрика