Tesla Terafactory Texas Update #189 in 4K: Shaping Perimeter Roads & Lots - 07/27/21 (4:30pm | 98°F)

Hey guys, it’s Randy! Today’s footage shows the updates on a hot and hazy day at the site. Some noticeable things we see today are the continued efforts to prep new roadways and the different types of parking lots around the perimeter of the site. Things are becoming much more clear as paths are being formed for the roads and additional lots we should see paved soon.

Here are today’s key takeaways:
-The northeast corner shows better shaping and forming of the roads that will be built here as we can see a mud slab poured atop the drainage pipe and a pretty distinct shape of the road that will follow the angled lines of the building, which I personally think is an extremely nice touch! It also looks like this road could be much wider than just a 2-lane road as we can see widening taking place nearest the storage containers extending the lane turning from the south road coming from HGR. Also, the GigaPress roof has more of the welded wire mesh and other materials delivered as well for the next phase of the roof construction.
-The south end of the BIW building shows the 2nd-level floor beams almost completely installed and workers are now placing stacks of metal decking to be spread later.
-The structural steel installation in the southwest corner continues to look good and we can see more columns have been erected near the red crane.
-On the west side of the GA building, we see yet another large section with the same pattern of trenches dug for the conduit we see for the new charging lot north of this one. We see that the smooth and prepped area to extend the latest paved lot we saw yesterday is sectioned off from this too, most likely to keep everyone off of it until the paving vehicles can arrive the next day. As for the north charging lot, we can see that more of the posts to hold the chargers are going in not only nearest the building, but now along the concrete slabs in the middle and edge of the lot nearest the road. We next see the work to widen the roadway area west of these lots as they work south from the north end.
-The BCP building has wall panels steadily being applied along with more roof insulation and both seem to be working north at about the same pace. We also now start to see the perimeter road taking shape north of this building and how it lines up with the one across from it in the northeast corner.
-We wrap up with the southern gap actively having structural steel going in as the structure expands south and we also have pretty much the same work happening in the northern gap as they expand to the north.

If you’re new here, please be sure to like, subscribe, and hit the notification bell if you want to be kept up-to-date with the latest content. If you enjoy it, please consider supporting the channel on Patreon via the links in the description or at the end of the video.

--------------------------------------------

Affiliate Links for Equipment Used or Recommended:

DJI Mavic Air 2 Fly More Combo w/Smart Controller: https://amzn.to/3pqD794
DJI Mavic Mini 2 Fly More Combo: https://amzn.to/3rtdLJH
DJI Mavic Mini Fly More Combo: https://amzn.to/34NZgq0
SanDisk 128gb Micro SD Card: https://amzn.to/3pqEftk

--------------------------------------------
Support Me On Patreon or PayPal

https://www.patreon.com/terafactorytexas

https://paypal.me/davismediasolutions

--------------------------------------------

Tesla Referral Code

https://ts.la/randy95094

--------------------------------------------

Date Filmed: 07-27-21
Time of Day: Late Afternoon - 4:30pm

--------------------------------------------

Social Media

Twitter: https://twitter.com/Terafactorytx
Instagram: https://www.instagram.com/terafactorytx/

--------------------------------------------

Additional Terafactory Texas Footage Channels
NOTE: We all film at different times throughout the day so check us all out in order to catch footage from certain times of the day.

@JeffRoberts - https://www.youtube.com/user/peterdog15
@JoeTegtmeyer - https://www.youtube.com/c/JoeTegtmeyer
@TxTerafactory - https://www.youtube.com/c/TexasTerafactory

--------------------------------------------

Giga Berlin Footage

The Wolfpack Berlin: https://www.youtube.com/c/thewolfpackberlin

--------------------------------------------

Music

Turn Up Burn Up - Diamond Ortiz
Six Seasons - Unicorn Heads

Видео Tesla Terafactory Texas Update #189 in 4K: Shaping Perimeter Roads & Lots - 07/27/21 (4:30pm | 98°F) канала Terafactory Texas
Показать
Комментарии отсутствуют
Введите заголовок:

Введите адрес ссылки:

Введите адрес видео с YouTube:

Зарегистрируйтесь или войдите с
Информация о видео
28 июля 2021 г. 18:32:44
00:24:50
Другие видео канала
Tesla Terafactory Texas Update #230 in 4K: Pond and Paving Focus 11/30/21 (5:00pm | 72°F)Tesla Terafactory Texas Update #230 in 4K: Pond and Paving Focus 11/30/21 (5:00pm | 72°F)Tesla Terafactory Texas Update #234 in 4K: Closing Up The North End 12/06/21 (4:45pm | 72°F)Tesla Terafactory Texas Update #234 in 4K: Closing Up The North End 12/06/21 (4:45pm | 72°F)Tesla Terafactory Texas Update #232 in 4K: Paving In Overdrive Pt2 12/02/21 (5:00pm | 78°F)Tesla Terafactory Texas Update #232 in 4K: Paving In Overdrive Pt2 12/02/21 (5:00pm | 78°F)Tesla Terafactory Texas Update #224 in 4K: Back on the Scene 11/16/21 (5:15pm | 78°F)Tesla Terafactory Texas Update #224 in 4K: Back on the Scene 11/16/21 (5:15pm | 78°F)Tesla Terafactory Texas Update #226 in 4K: Steel Erecting Nearly Complete 11/18/21 (4:45pm | 65°FTesla Terafactory Texas Update #226 in 4K: Steel Erecting Nearly Complete 11/18/21 (4:45pm | 65°FTesla Terafactory Texas Update #231 in 4K: Paving In Overdrive 12/01/21 (4:45pm | 76°F)Tesla Terafactory Texas Update #231 in 4K: Paving In Overdrive 12/01/21 (4:45pm | 76°F)Tesla Terafactory Texas Update #233 in 4K: Drainage System Complete??? 12/06/21 (4:30pm | 62°F)Tesla Terafactory Texas Update #233 in 4K: Drainage System Complete??? 12/06/21 (4:30pm | 62°F)Tesla Terafactory Texas Update #228 in 4K: Pre-Holiday Push 11/23/21 (5:00pm | 68°F)Tesla Terafactory Texas Update #228 in 4K: Pre-Holiday Push 11/23/21 (5:00pm | 68°F)Tesla Terafactory Texas Update #227 in 4K: Major Pond Updates 11/22/21 (5:00pm | 65°F)Tesla Terafactory Texas Update #227 in 4K: Major Pond Updates 11/22/21 (5:00pm | 65°F)Tesla Terafactory Texas Update #221 in 4K: New Massive Bridge Cranes Arrive 10/11/21 (4:45pm | 84°F)Tesla Terafactory Texas Update #221 in 4K: New Massive Bridge Cranes Arrive 10/11/21 (4:45pm | 84°F)Tesla Terafactory Texas Update #225 in 4K: Mega Drainage Structures 11/17/21 (5:15pm | 82°F)Tesla Terafactory Texas Update #225 in 4K: Mega Drainage Structures 11/17/21 (5:15pm | 82°F)Tesla Terafactory Texas Update #190 in 4K: Paving Resumes - 07/28/21 (5:00pm | 98°F)Tesla Terafactory Texas Update #190 in 4K: Paving Resumes - 07/28/21 (5:00pm | 98°F)Tesla Terafactory Texas Update #184 in 4K: Working Through The Rain - 07/14/21 (5:15pm | 79°F)Tesla Terafactory Texas Update #184 in 4K: Working Through The Rain - 07/14/21 (5:15pm | 79°F)Tesla Terafactory Texas Update #148 in 4K: Bobcat Project New Foundation - 05/04/21 (5:00pm | 81°F)Tesla Terafactory Texas Update #148 in 4K: Bobcat Project New Foundation - 05/04/21 (5:00pm | 81°F)Tesla Terafactory Texas Update #222 in 4K: Soaked But Still Progressing 10/14/21 (5:15pm | 78°F)Tesla Terafactory Texas Update #222 in 4K: Soaked But Still Progressing 10/14/21 (5:15pm | 78°F)Tesla Terafactory Texas Update #229 in 4K: Review Complete 11/29/21 (3:30pm | 72°F)Tesla Terafactory Texas Update #229 in 4K: Review Complete 11/29/21 (3:30pm | 72°F)Tesla Terafactory Texas Update #215 in 4K: All West-facing Panels Installed 09/22/21 (7:00pm | 82°F)Tesla Terafactory Texas Update #215 in 4K: All West-facing Panels Installed 09/22/21 (7:00pm | 82°F)Tesla Terafactory Texas Update #220 in 4K: New Tesla Headquarters 10/07/21 (4:15pm | 92°F)Tesla Terafactory Texas Update #220 in 4K: New Tesla Headquarters 10/07/21 (4:15pm | 92°F)Tesla Gigafactory Texas 12 March 2021 Cyber Truck & Model Y Factory Construction Update (07:30AM)Tesla Gigafactory Texas 12 March 2021 Cyber Truck & Model Y Factory Construction Update (07:30AM)
Яндекс.Метрика