Step 1. Analysis of the existing elements of project planning
It begins with the formation of work teams, usually by component, according to the
PM4R Agile roles described in chapter 3. Once the teams are formed, they perform
the analysis of the existing project planning elements, such as the project plan (PEP,
AOP in the case of the IDB), the Work Breakdown Structure (WBS), the schedule, the
S curve, etc. If the WBS is not available, the team, with the help of the PM4R Agile
experts, will have to develop it, since it is the base for selection of the priority works
that will be included in the PM4R Agile plan. If the component you are working on is
already in execution, ensure that only the works that have not been completed yes
are considered for inclusion in the WBS.
Видео Step 1. Analysis of the existing elements of project planning канала pm4r
PM4R Agile roles described in chapter 3. Once the teams are formed, they perform
the analysis of the existing project planning elements, such as the project plan (PEP,
AOP in the case of the IDB), the Work Breakdown Structure (WBS), the schedule, the
S curve, etc. If the WBS is not available, the team, with the help of the PM4R Agile
experts, will have to develop it, since it is the base for selection of the priority works
that will be included in the PM4R Agile plan. If the component you are working on is
already in execution, ensure that only the works that have not been completed yes
are considered for inclusion in the WBS.
Видео Step 1. Analysis of the existing elements of project planning канала pm4r
Показать
Комментарии отсутствуют
Информация о видео
Другие видео канала
Procurement MatrixLos obstáculos más frecuentes en la negociación y cómo superarlosLa nueva certificación de PMI ACPPaso 3. Desarrollo del plan PM4R AgileStakeholder MatrixProceso Analisis de los elementos de planificación del proyectoEl Liderazgo en los Equipos de los Proyectos de Desarrollo – PM4R LeadershipPaso 5. Implementacióndel plan PM4R AgileWebinar La evolución de las Mejores Prácticas en Dirección de ProyectosTaller de Manejo del Conflicto5 Proceso Implementación del Plan PM4R AgileStep 2. Selection of the priority worksPM4R Procurement Matrix4 Introducción Asignación de responsabilidades2 Introducción Selección de trabajos prioritariosPM4R scheduleWebinar La negociación como medio para crear valor en los proyectos de desarrolloWebinar PM4R Cloud Dar y recibir feedback2 Proceso Selección de trabajos prioritariosAdministración del propio tiempo en la gestión de proyectos parte I5 Proceso Implementación del Plan PM4R Agile