Step 3. Development of the PM4R Agile plan
It is recommended that the PM4R Agile plan comprises a planning horizon of three
months. These three months are organized in 6 sprints of two weeks each. For their
realization, the work team meets to determine which elements of the set prioritized
work will be developed and delivered in each sprint. If a work lasts estimated more
than two weeks, that is, a sprint, it must be broken down into smaller elements.
The suggested way to make the plan is drawing six columns on the wall representing
the six sprints. Each sprint should have a beginning and ending date, and then, the
team members place the of work, represented by post its, in each one of the
columns. It is important that the workload in each sprint be balanced, since there is a
tendency for more work schedule in the initial and final sprints.
Once the work is placed in the sprints, the work team validates the plan with the
owner of the product and the agile leader. It is fundamental that the plan is realistic,
since it represents a commitment that the entire team must fulfill.
Видео Step 3. Development of the PM4R Agile plan канала pm4r
months. These three months are organized in 6 sprints of two weeks each. For their
realization, the work team meets to determine which elements of the set prioritized
work will be developed and delivered in each sprint. If a work lasts estimated more
than two weeks, that is, a sprint, it must be broken down into smaller elements.
The suggested way to make the plan is drawing six columns on the wall representing
the six sprints. Each sprint should have a beginning and ending date, and then, the
team members place the of work, represented by post its, in each one of the
columns. It is important that the workload in each sprint be balanced, since there is a
tendency for more work schedule in the initial and final sprints.
Once the work is placed in the sprints, the work team validates the plan with the
owner of the product and the agile leader. It is fundamental that the plan is realistic,
since it represents a commitment that the entire team must fulfill.
Видео Step 3. Development of the PM4R Agile plan канала pm4r
Показать
Комментарии отсутствуют
Информация о видео
Другие видео канала
Procurement MatrixLos obstáculos más frecuentes en la negociación y cómo superarlosLa nueva certificación de PMI ACPPaso 3. Desarrollo del plan PM4R AgileStakeholder MatrixProceso Analisis de los elementos de planificación del proyectoEl Liderazgo en los Equipos de los Proyectos de Desarrollo – PM4R LeadershipPaso 5. Implementacióndel plan PM4R AgileWebinar La evolución de las Mejores Prácticas en Dirección de ProyectosTaller de Manejo del Conflicto5 Proceso Implementación del Plan PM4R AgileStep 2. Selection of the priority worksPM4R Procurement Matrix4 Introducción Asignación de responsabilidades2 Introducción Selección de trabajos prioritariosPM4R scheduleWebinar La negociación como medio para crear valor en los proyectos de desarrolloWebinar PM4R Cloud Dar y recibir feedback2 Proceso Selección de trabajos prioritariosAdministración del propio tiempo en la gestión de proyectos parte I5 Proceso Implementación del Plan PM4R Agile