Under-Shannon Crossing | Athlone Main Drainage Scheme | Uisce Éireann
Uisce Éireann, working in partnership with Westmeath County Council, has commenced works to upgrade the Athlone sewer network. When completed, this project will reduce the risk of sewer flooding in Athlone and address non-compliant sewer overflows into the River Shannon. It will also improve the capacity of the sewer network allowing for current and future population growth.
Most recently the first underground crossing of the mighty River Shannon was successfully completed. These tunnelling works which began in September 2023 in the Deerpark/Showgrounds area of Athlone were scheduled for completion in early 2024. The tunnel boring machine paved its way under the river, installing this critical pipeline and has now successfully arrived at Burgess Park.
The next phase of tunnelling works will commence this week from Burgess Park to Wolf Tone Terrace which will take approximately two months to complete. Following on from these works, tunnelling will commence from Golden Island to Paynes Lane with an estimated completion date of Summer 2024.
For more on this project, check out https://www.water.ie/athlone-main-drainage-scheme/
Follow @IrishWater on Twitter (https://www.twitter.com/irishwater) for news and updates from Uisce Éireann.
Follow us on Facebook at https://www.facebook.com/IrishWater/.
Follow @IWCare on Twitter (https://www.twitter.com/iwcare) for customer care queries and water service updates.
Follow us on LinkedIn (https://www.linkedin.com/company/irish-water/) for company news, updates and careers.
About Us
We are Uisce Éireann. As Ireland’s national regulated water utility, every day we are responsible for the delivery of secure, safe, and sustainable water services for the people of Ireland.
Our job is to deliver the highest quality drinking water to your taps every day and ensure that wastewater is properly treated and safely returned to the environment.
Our Purpose
To rise to the challenge of delivering transformative water services that enable communities to thrive.
Our Vision
A sustainable Ireland where water is respected and protected, for the planet and all the lives it supports.
Видео Under-Shannon Crossing | Athlone Main Drainage Scheme | Uisce Éireann канала Uisce Eireann Irish Water
Most recently the first underground crossing of the mighty River Shannon was successfully completed. These tunnelling works which began in September 2023 in the Deerpark/Showgrounds area of Athlone were scheduled for completion in early 2024. The tunnel boring machine paved its way under the river, installing this critical pipeline and has now successfully arrived at Burgess Park.
The next phase of tunnelling works will commence this week from Burgess Park to Wolf Tone Terrace which will take approximately two months to complete. Following on from these works, tunnelling will commence from Golden Island to Paynes Lane with an estimated completion date of Summer 2024.
For more on this project, check out https://www.water.ie/athlone-main-drainage-scheme/
Follow @IrishWater on Twitter (https://www.twitter.com/irishwater) for news and updates from Uisce Éireann.
Follow us on Facebook at https://www.facebook.com/IrishWater/.
Follow @IWCare on Twitter (https://www.twitter.com/iwcare) for customer care queries and water service updates.
Follow us on LinkedIn (https://www.linkedin.com/company/irish-water/) for company news, updates and careers.
About Us
We are Uisce Éireann. As Ireland’s national regulated water utility, every day we are responsible for the delivery of secure, safe, and sustainable water services for the people of Ireland.
Our job is to deliver the highest quality drinking water to your taps every day and ensure that wastewater is properly treated and safely returned to the environment.
Our Purpose
To rise to the challenge of delivering transformative water services that enable communities to thrive.
Our Vision
A sustainable Ireland where water is respected and protected, for the planet and all the lives it supports.
Видео Under-Shannon Crossing | Athlone Main Drainage Scheme | Uisce Éireann канала Uisce Eireann Irish Water
Показать
Комментарии отсутствуют
Информация о видео
29 февраля 2024 г. 20:44:54
00:00:42
Другие видео канала
Lead in Drinking Water Mitigation Plan | Projects & Plans | Irish WaterWater Stewardship Hub | For Business | Uisce Éireann#FixingLeaks | Blessington Road, Naas, Co. Kildare | Leakage Reduction Programme | Uisce ÉireannStillorgan Reservoir Upgrade Project | Our Projects | Uisce ÉireannEarly Careers Professionals | Graduate Programme | Uisce ÉireannNew wastewater treatment plant for Athea | Our Projects | Irish WaterThink Before You Flush this Summer | Uisce Éireann#FixingLeaks | Oliver Plunkett Street, Cork City | Leakage Reduction Programme | Uisce ÉireannUisce Éireann Television Advert - 15’Uisce Éireann - Fógra Teilifíse Gaeilge – 15'Finding water service updates on Twitter | Useful Tips | Irish WaterYoughal WwTP Opening | Wastewater Treatment | Irish WaterScience Week Outside Broadcast | Lough Guitane | Uisce ÉireannHospitality Industry | Water Conservation | Irish WaterCobh Networks Contract Completion | Cork Lower Harbour | Uisce ÉireannDetect LeaksDistrict Metering Areas Explained | Leakage Reduction Programme | Uisce ÉireannConstruction Phase QA Process | Chapter 5 | New Connections | Uisce ÉireannEliminating Raw Sewage in Bundoran | Wastewater Treatment | Uisce Éireann#FixingLeaks | Rhode, Co. Offaly | Leakage Reduction Programme | Uisce Éireann