ADU Garage Conversion 428 SQFT E:20 The Inside Reveal

It's done. Finally done after 6 months of construction for an existing attached garage to a 1-bd and 1-ba garage ADU.

Blueprint process started on 6/29/2020
Construction started on 12/11/2020
Blueprints approved by city on 1/08/2021
Construction completed on 6/11/2021

Almost a full year. 7 months for the blueprint approval and 6 months for construction with one month overlap = 12 months total.

Interior and exterior designer = Josie
Floorplan developed by = Manny
Constructed by = Small mom-and-pop investing, flipping, and construction company who won't take online referrals.