Project 2016 for Beginners Part 13: How to Set Project Milestones in MS Project 2016

Get a FREE 3-hour Project 2016 training course here ► https://simonsezit.leadpages.co/free-project-2016-course/

During this Microsoft Project 2016 training tutorial video, we will demonstrate the process of setting milestones, which are useful in denoting significant events in a project and giving a realistic summary of the key points in a project. We will also show you how to filter the timeline so that what will be shown are all the milestones.

Checkout some of our other training on YouTube:

Excel 2016 training: https://www.youtube.com/playlist?list=PLzj7TwUeMQ3hFUdlWMkTLZL-Fr3oRGN35

Project 2013 training: https://www.youtube.com/playlist?list=PLzj7TwUeMQ3i1QJ6-Z91KRjFg5dzacD1O

VBA for Excel tutorials: https://www.youtube.com/playlist?list=PLzj7TwUeMQ3hWRi0mgxdyWkT0QaYKuBGZ

Visio 2013 for beginners: https://www.youtube.com/playlist?list=PLzj7TwUeMQ3jpAwkTGD6hGNxF8ML_FfsF

SharePoint 2013 training: https://www.youtube.com/playlist?list=PLzj7TwUeMQ3jloGuvewOe0Iv1EE2POKge

Stay in touch:
SimonSezIT.com: http://www.simonsezit.com/
StreamSkill.com: http://streamskill.com/
YouTube Channel: http://bit.ly/foiItB
Facebook: http://on.fb.me/14m8Rwl
Twitter: http://bit.ly/177EU5J
Google+: http://bit.ly/11JbHdb

If you enjoyed the video, please give a "thumbs up" and subscribe to the channel ;-)

Welcome back to our course on Project 2016. In this section we’re going to look at Milestones. And Milestones are used to denote significant points or events in a project. Usually milestone tasks have zero duration but Project 2016 does allow milestones with non-zero durations as well. Milestones are used for a number of different purposes.

And amongst the most important ones are as a way of providing a management snapshot of progress on a project. So there is for example a particular report called a Milestone Report where you can just view the key milestones in the project and get a summary of where you are in terms of those milestones which in turn gives you a good idea of general progress on the project. They can also be used to show you what’s coming up next, what’s happening say over the next week or the next month or the next few days.

And very often milestones are associated with a payment schedule of some sort. So for example, when a particular point is reached in a project there may be a payment to make. Now what I’m going to do with the wedding project is to take some of the existing tasks and turn them into milestones. And I may well introduce one or two new milestones as I go through. Before I start note what I’ve done with the project at this stage. This is version 03 of the project. I have collapsed all of the summary tasks.

Note that when I do this you can’t see all of the dependencies. So for instance, there is a dependency between a task in Wedding day and the setting of the wedding date. But because Wedding day is collapsed you can’t see that link. If I expand Wedding day that link is now visible Note the link from Book wedding venue, task 40, up to Set wedding date. But when Wedding day as a summary task is collapsed you can no longer see that link. So this just emphasizes the point that when you’re looking at a project with some summary task collapse you need to be careful at what you’re interpreting because some elements of the project may have become invisible even though they’re actually quite significant.

Now one very important aspect of Milestones is that generally speaking although I should say there are exceptions, but generally speaking because a milestone is a task of zero duration it is assumed that there is little or no work associated with the milestone itself. If I take task 4 here, Set wedding date, if that doesn’t actually involve any significant amount of work I could make it into a milestone. But what I’m actually going to do on this occasion is to insert specifically a milestone which indicates when that task has been completed. So I’m going to select the task below it which is basically a blank row and then on the Task Tab in the Insert Group I’m going to say Insert Task.

Now that task I’m going to rename to Wedding date set. So that’s basically a statement that something has happened. It isn’t something to do itself. And then in the duration for that task I’m going to change it to zero days which will make it into a milestone. And the default notation, the default symbol in a Gantt Chart for a milestone is a diamond. So now I’m going to select Set wedding date and select Wedding date set and link them in the usual way. And I have my first Milestone in my project.

Sorry, we couldn't fit the entire video transcription here since YouTube only allows 5000 characters.

Видео Project 2016 for Beginners Part 13: How to Set Project Milestones in MS Project 2016 канала Simon Sez IT
Показать
Комментарии отсутствуют
Введите заголовок:

Введите адрес ссылки:

Введите адрес видео с YouTube:

Зарегистрируйтесь или войдите с
Информация о видео
14 июня 2016 г. 23:00:02
00:20:42
Другие видео канала
Learn how to use Photoshop Elements 11 - Part 33 -  How to Resize a Picture in PhotoshopLearn how to use Photoshop Elements 11 - Part 33 - How to Resize a Picture in PhotoshopMicrosoft Excel 2010 Advanced Training - Part 17 - Charting & Graphing Financial InformationMicrosoft Excel 2010 Advanced Training - Part 17 - Charting & Graphing Financial InformationMicrosoft Excel 365 Tutorial: 3+ Hours of Advanced Excel TrainingMicrosoft Excel 365 Tutorial: 3+ Hours of Advanced Excel TrainingDreamweaver CS6 Training - Part 29 - How to Modify a Table in a Web page - Create a Website CourseDreamweaver CS6 Training - Part 29 - How to Modify a Table in a Web page - Create a Website CourseHow to Stay Safe Online: Cyber Security Awareness for EveryoneHow to Stay Safe Online: Cyber Security Awareness for EveryoneMicrosoft SharePoint Online Interface Explained - Office 365Microsoft SharePoint Online Interface Explained - Office 365Microsoft Project 2016 Course for Project Management - Learn MS Project 2016 Tutorial - Part 5Microsoft Project 2016 Course for Project Management - Learn MS Project 2016 Tutorial - Part 5QuickBooks 2018 Training Tutorial Part 4: Setting Preferences in QuickBooks - Part 2QuickBooks 2018 Training Tutorial Part 4: Setting Preferences in QuickBooks - Part 2Windows 11 Introduction: 7 Top Tips and TricksWindows 11 Introduction: 7 Top Tips and TricksUnderstanding VBA Code in Microsoft Excel - VBA for BeginnersUnderstanding VBA Code in Microsoft Excel - VBA for BeginnersMicrosoft Project 2016 Course for Project Management - Learn MS Project 2016 Tutorial - Part 6Microsoft Project 2016 Course for Project Management - Learn MS Project 2016 Tutorial - Part 6Creating Your First Project in Microsoft Project - 1 Hour MS Project Tutorial - Part 2Creating Your First Project in Microsoft Project - 1 Hour MS Project Tutorial - Part 2Using Summary Tasks for Your MS Project 2019 Project PlanUsing Summary Tasks for Your MS Project 2019 Project PlanTop Ten Excel Formulas and Functions - IF, VLOOKUP, PMT, INDEX MATCH - Excel TutorialTop Ten Excel Formulas and Functions - IF, VLOOKUP, PMT, INDEX MATCH - Excel TutorialThe Ultimate MS Excel Crash Course: 6-Hour Microsoft Excel 2016 Tutorial for BeginnersThe Ultimate MS Excel Crash Course: 6-Hour Microsoft Excel 2016 Tutorial for BeginnersMicrosoft Office 2021/365 for Beginners: 9+ Hours of Excel, Word, and PowerPoint TrainingMicrosoft Office 2021/365 for Beginners: 9+ Hours of Excel, Word, and PowerPoint TrainingCreating an Interactive Dashboard in Excel Using Pivot Tables, Pivot Charts and SlicersCreating an Interactive Dashboard in Excel Using Pivot Tables, Pivot Charts and SlicersUsing Cross-Functional Flowcharts in Microsoft Visio 2019Using Cross-Functional Flowcharts in Microsoft Visio 2019How to Link to Excel Data from Microsoft WordHow to Link to Excel Data from Microsoft WordHow to Add and Work With Layers in Photoshop Elements 2018 - Part 2How to Add and Work With Layers in Photoshop Elements 2018 - Part 2Financial Forecasting and Modeling 2+ Hour Course!Financial Forecasting and Modeling 2+ Hour Course!
Яндекс.Метрика