Laguna Farms - November 30, 2023

Construction progress has been start and stop for quite some time. A number of new certificates of occupancy have been issued, however, with 27 fourplexes receiving certificates of occupancy to date. Construction in phase 1 is nearing completion, with all units finished with exterior and well underway with various trades on the interior. The clubhouse is framed and complete on the exterior, and the pool construction is in progress. The two commercial mixed-use buildings at the entrance are in framing. Phase 2 is in various stages of roofing and interior trade work. Check out the latest video below and please let your designated FIG agent know if you have any questions.