USACE Westlake Alternate Care Facility
Bulley & Andrews (B&A) served as the design/build contractor that led the construction effort to reopen the former Westlake Hospital in Melrose Park, IL. The previously shuttered 230-bed facility is temporarily reopening as an Alternate Care Facility (ACF) for COVID-19 patients. The facility offers 430 patient beds and provides acute and intensive care.
Working under the direction of the U.S. Army Corps of Engineers, the design/build team worked 24/7 to complete the project in three weeks. Performing with strict adherence to COVID-19 specific safety guidelines, the project required expanded Personal Protective Equipment (PPE) usage and rigorous COVID-19 centric screening which involved temperature readings upon entry to the jobsite. Over 350 trades people worked tirelessly to ensure the facility was ready for the “peak” in COVID-19 cases the State of Illinois anticipates in mid-May.
B&A and their partners were able to mobilize for this project within 18 hours from notice to proceed in order to execute the ambitious schedule. Tim Puntillo, President of Bulley & Andrews, noted, “the opportunity to apply our professional skills to something that has such a tangible impact on the community is the chance of a lifetime. And to do it alongside our most trusted and respected industry partners is one of the highlights of my career and Bulley & Andrews’ history.”
The project, which operated around-the-clock from inception to completion in order to finish on time, logged over 37,750 labor hours with no lost time incidents. B&A self-performed over 10,000 labor hours with no lost time incidents.
Видео USACE Westlake Alternate Care Facility канала Bulley & Andrews
Working under the direction of the U.S. Army Corps of Engineers, the design/build team worked 24/7 to complete the project in three weeks. Performing with strict adherence to COVID-19 specific safety guidelines, the project required expanded Personal Protective Equipment (PPE) usage and rigorous COVID-19 centric screening which involved temperature readings upon entry to the jobsite. Over 350 trades people worked tirelessly to ensure the facility was ready for the “peak” in COVID-19 cases the State of Illinois anticipates in mid-May.
B&A and their partners were able to mobilize for this project within 18 hours from notice to proceed in order to execute the ambitious schedule. Tim Puntillo, President of Bulley & Andrews, noted, “the opportunity to apply our professional skills to something that has such a tangible impact on the community is the chance of a lifetime. And to do it alongside our most trusted and respected industry partners is one of the highlights of my career and Bulley & Andrews’ history.”
The project, which operated around-the-clock from inception to completion in order to finish on time, logged over 37,750 labor hours with no lost time incidents. B&A self-performed over 10,000 labor hours with no lost time incidents.
Видео USACE Westlake Alternate Care Facility канала Bulley & Andrews
Показать
Комментарии отсутствуют
Информация о видео
Другие видео канала
B&A's relationship with S&C Electric CompanyUniversity Club of Chicago Rooftop Construction Time-LapseCST The Yard Construction TimelapseRobie House Historical RestorationNorthwestern University Kresge Hall RenovationLeveraging Safety + TechnologyNorth Central College | New Health Sciences & Engineering Academic FacilityBA Headquarters | Office ReconfigurationAllan E. Bulley, Jr. and Joe Antunovich receive 2018 Pro Musica Award from DePaul UniversityCommunity Consolidated School District 181: Hinsdale Middle School TimelapseCanstruction 2018 Black Canther VideoRestoring the Gilding at The Belden StratfordB&A COVID-19 Vaccination DayThe City of Evanston's Robert Crown Community Center, Ice Complex and LibraryB&A Helps The University Club of Chicago Expand on TraditionsSchiller Park School District 81: Washington Elementary SchoolB&A Headquarters Construction Time LapseRush Copley NICUHoward Brown Health | Broadway Youth CenterFenwick High School's new, 330-space parking garage.