Hey guys, it’s Randy! Today’s video shows the site buzzing as usual when the weather is clear and dry. There were definitely some interesting developments and noted progress taking place even as I flew, the most notable of which is that the erecting of steel in the southern gap has started! There’s a lot to cover so let's jump into the footage.

Here are today’s key takeaways:
-The GigaPress area shows more columns have been erected which, is the row nearest the crane shown at center. We also see that horizontal crossbeams are also being installed. They were about to move this large one into place at the start of filming and towards the end when I was wrapping up, I flew back by again to confirm that it was in fact in place and we can see the next one to be installed on the truck pictured.
-Next, we had previously seen the early makings of a new road branching off from HGR heading south between the power transmission line towers and here we can see it as it starts to become more clearly defined. As for the main intersection on the east side of the highway, we can see that tar has been applied in the new area of the right turn lane and we’ll probably see the same happen on the other side of the street soon as well. The chances of this being paved on Tuesday are pretty high since that’s usually an immediate step after the initial layer of tar is applied.
-The southwest corner shows an updated look at the structural steel being erected for the angled section of the corner. We also can see across the structure at the progress with filling the rest of this large section.
-We next get a quick look on the west side of the GA building at the progress of the inner wall that was framed out in my last video and we can see that panel installation is already moving along quickly on the top level. Further north on this side, we see the conduit in the process of being buried and the large section that was shown spanning across the road is now covered and the road path has been restored.
-The southern gap surprisingly shows that the erecting of the steel has started in this area and they already have the northeast corner already up and we can see the next column south of this in place. My guess is that they’ll build out south until about where the crane is currently placed and just repeat that pattern in rows working to the west until 3 sections north-to-south and 5 sections east-to-west have been erected and then move the crane south the same amount of spaces and just repeat all the way down. Let me know what you guys think in the comments below!
-Work on the BCP roof continues as we see more of the concrete mix material has been applied.
-Lastly, we see in the Bobcat Project area that efforts are underway to spread and apply more fill soil east of the main foundation currently in place.

If you’re new here, please be sure to like, subscribe, and hit the notification bell if you want to be kept up-to-date with the latest content. If you enjoy it, please consider supporting the channel on Patreon via the links in the description or at the end of the video.

--------------------------------------------

Affiliate Links for Equipment Used or Recommended:

DJI Mavic Air 2 Fly More Combo w/Smart Controller: https://amzn.to/3pqD794
DJI Mavic Mini 2 Fly More Combo: https://amzn.to/3rtdLJH
DJI Mavic Mini Fly More Combo: https://amzn.to/34NZgq0
SanDisk 128gb Micro SD Card: https://amzn.to/3pqEftk

--------------------------------------------
Support Me On Patreon or PayPal

https://www.patreon.com/terafactorytexas

https://paypal.me/davismediasolutions

--------------------------------------------

Tesla Referral Code

https://ts.la/randy95094

--------------------------------------------

Date Filmed: 07-12-21
Time of Day: Late Afternoon - 5:15pm

--------------------------------------------

Social Media

Twitter: https://twitter.com/Terafactorytx
Instagram: https://www.instagram.com/terafactorytx/

--------------------------------------------

Additional Terafactory Texas Footage Channels
NOTE: We all film at different times throughout the day so check us all out in order to catch footage from certain times of the day.

@JeffRoberts - https://www.youtube.com/user/peterdog15
@JoeTegtmeyer - https://www.youtube.com/c/JoeTegtmeyer
@TxTerafactory - https://www.youtube.com/c/TexasTerafactory

--------------------------------------------

Giga Berlin Footage

The Wolfpack Berlin: https://www.youtube.com/c/thewolfpackberlin

--------------------------------------------

Music

Turn Up Burn Up - Diamond Ortiz
Early April - Unicorn Heads

Видео Tesla Terafactory Texas Update #182 in 4K: New Steel Going Up - 07/12/21 (5:15pm | 85°F) канала Terafactory Texas
Показать
Комментарии отсутствуют
Введите заголовок:

Введите адрес ссылки:

Введите адрес видео с YouTube:

Зарегистрируйтесь или войдите с
Информация о видео
13 июля 2021 г. 17:26:48
00:22:44
Другие видео канала
Tesla Terafactory Texas Update #216 in 4K: Many Exterior Updates 09/23/21 (7:15pm | 80°F)Tesla Terafactory Texas Update #216 in 4K: Many Exterior Updates 09/23/21 (7:15pm | 80°F)Tesla Terafactory Texas Update #231 in 4K: Paving In Overdrive 12/01/21 (4:45pm | 76°F)Tesla Terafactory Texas Update #231 in 4K: Paving In Overdrive 12/01/21 (4:45pm | 76°F)Tesla Terafactory Texas Update #219 in 4K: New Southern Gap Steel Going Up 10/04/21 (5:15pm | 90°F)Tesla Terafactory Texas Update #219 in 4K: New Southern Gap Steel Going Up 10/04/21 (5:15pm | 90°F)Tesla Terafactory Texas Update #148 in 4K: Bobcat Project New Foundation - 05/04/21 (5:00pm | 81°F)Tesla Terafactory Texas Update #148 in 4K: Bobcat Project New Foundation - 05/04/21 (5:00pm | 81°F)Tesla Terafactory Texas Update #232 in 4K: Paving In Overdrive Pt2 12/02/21 (5:00pm | 78°F)Tesla Terafactory Texas Update #232 in 4K: Paving In Overdrive Pt2 12/02/21 (5:00pm | 78°F)Tesla Terafactory Texas Update #218 in 4K: More Road & Exterior Updates 09/30/21 (5:30pm | 94°F)Tesla Terafactory Texas Update #218 in 4K: More Road & Exterior Updates 09/30/21 (5:30pm | 94°F)Tesla Terafactory Texas Update #217 in 4K: Prepping For Southern Gap Steel 09/27/21 (5:15pm | 92°F)Tesla Terafactory Texas Update #217 in 4K: Prepping For Southern Gap Steel 09/27/21 (5:15pm | 92°F)Tesla Terafactory Texas Update #230 in 4K: Pond and Paving Focus 11/30/21 (5:00pm | 72°F)Tesla Terafactory Texas Update #230 in 4K: Pond and Paving Focus 11/30/21 (5:00pm | 72°F)Tesla Terafactory Texas Update #109 in 4K:  Back To Work - 02/22/21 (5:15pm | 73°F)Tesla Terafactory Texas Update #109 in 4K: Back To Work - 02/22/21 (5:15pm | 73°F)Tesla Terafactory Texas Update #137: Amazing Battery Structure Progress - 04/12/21 (5:00pm | 89°F)Tesla Terafactory Texas Update #137: Amazing Battery Structure Progress - 04/12/21 (5:00pm | 89°F)Tesla Terafactory Texas Update #224 in 4K: Back on the Scene 11/16/21 (5:15pm | 78°F)Tesla Terafactory Texas Update #224 in 4K: Back on the Scene 11/16/21 (5:15pm | 78°F)Tesla Terafactory Texas Update #128 in 4K: Severe Storms On The Way - 03/24/21 (5:00pm | 71°F)Tesla Terafactory Texas Update #128 in 4K: Severe Storms On The Way - 03/24/21 (5:00pm | 71°F)Tesla Terafactory Texas Update #145 in 4K: Two For One - 04/28/21 (5:15pm | 82°F)Tesla Terafactory Texas Update #145 in 4K: Two For One - 04/28/21 (5:15pm | 82°F)Tesla Terafactory Texas Update #112: Giga Press Furnace Installation Begins - 02/25/21 5:00pm | 55°FTesla Terafactory Texas Update #112: Giga Press Furnace Installation Begins - 02/25/21 5:00pm | 55°FTesla Terafactory Texas Update #221 in 4K: New Massive Bridge Cranes Arrive 10/11/21 (4:45pm | 84°F)Tesla Terafactory Texas Update #221 in 4K: New Massive Bridge Cranes Arrive 10/11/21 (4:45pm | 84°F)Tesla Terafactory Texas Update #113 in 4K: Nope - 02/26/21 (4:30pm | 62°F)Tesla Terafactory Texas Update #113 in 4K: Nope - 02/26/21 (4:30pm | 62°F)Tesla Terafactory Texas Update #234 in 4K: Closing Up The North End 12/06/21 (4:45pm | 72°F)Tesla Terafactory Texas Update #234 in 4K: Closing Up The North End 12/06/21 (4:45pm | 72°F)Tesla Terafactory Texas Update #180 in 4K: Superchargers Are Now Live - 07/08/21 (5:00pm | 84°F)Tesla Terafactory Texas Update #180 in 4K: Superchargers Are Now Live - 07/08/21 (5:00pm | 84°F)Tesla Terafactory Texas Update #134 in 4K: Exploring Deliveries - 04/05/21 (5:00pm | 79°F)Tesla Terafactory Texas Update #134 in 4K: Exploring Deliveries - 04/05/21 (5:00pm | 79°F)Tesla Terafactory Texas Update #222 in 4K: Soaked But Still Progressing 10/14/21 (5:15pm | 78°F)Tesla Terafactory Texas Update #222 in 4K: Soaked But Still Progressing 10/14/21 (5:15pm | 78°F)
Яндекс.Метрика