This is part 5 of a 5 part series on wind power in general and offshore wind farms in particular. In this section we go into how wind farms are developed, constructed and operated.

Contents:
00:00 Introduction
00:14 Contents
01:44 Recap
03:00 Wind farm allocation process
07:00 Development of the wind farm layout
11:37 The marshalling harbour
14:29 The heavy lift vessel
16:26 Installing monopile foundations
23:17 Installing jacket foundations
29:02 The cable laying vessel
32:01 The jackup vessel
37:36 The O and M port
40:12 The CTV
43:05 The SOV
47:07 Control rooms
49:25 Summary

Van Oord (Cable laying)
https://www.vanoord.com/

Ampleman dynamic gangway
https://www.ampelmann.nl/

Netherlands targets 70GW offshore wind
https://www.offshorewind.biz/2022/09/19/the-netherlands-sets-70-gw-offshore-wind-target-for-2050-plans-large-scale-green-hydrogen-production-and-energy-hubs/#:~:text=Advertisement-,The%20Netherlands%20Sets%2070%20GW%20Offshore%20Wind%20Target%20for%202050,Hydrogen%20Production%20and%20Energy%20Hubs&text=The%20Dutch%20Government%20has%20set,could%20be%20installed%20by%202040.

Some links to global climate change information:

https://skepticalscience.com/argument...
https://climate.nasa.gov/scientific-c...

Thanks for watching!

Видео Introduction to offshore wind part 5 канала drawingboard82
Показать
Комментарии отсутствуют
Введите заголовок:

Введите адрес ссылки:

Введите адрес видео с YouTube:

Зарегистрируйтесь или войдите с
Информация о видео
25 сентября 2022 г. 15:03:55
00:54:12
Яндекс.Метрика