PMBOK® Guide : Perform Integrated Change Control Change Request Flow
You can explore the videos for the complete course here https://www.izenbridge.com/pmp/online-course/
This video helps us in visualizing how to change request flows among various processes.
What is a Change Request? It is a tool for a change in the established plan or project document. So we should have a plan in place before we raise a change request.
Initiating and planning group has nothing to do with Change Request. These process groups don’t take change request as input & most of the time not as output (Procurement planning being an exception).
Executing and Monitoring & Control process groups deal with changes. In this video, you will see how the change request gets generated at various places.
In Executing Process Group you may or may not realize Change Requests. Change Requests goes directly to Integrated Change Control for further action. In case you don’t realize any change then the output is Work Performance Data (WPD), which go to the respective Knowledge Area Controlling Process. Here WPD can either generate another change requests or Work Performance Information (WPI). In the case of WPI as an output, it goes to Monitoring & Control where there are 2 possibilities, one is change request being generated, else Work Performance Report is generated. In the case of Change Request, it goes to “Approve/Reject/Deferred.”
Once a change request is received, the project team should not act on it immediately. They should first do impact analysis, it is then sent to respective stakeholder for decision making followed by a decision on the change requests. CRs can be approved, reject or deferred. Then these changes are logged in ChangeLog, a repository of detail of all the changes.
Then based on the changelog update, the project management plan is updated followed by communicating it to respective stakeholders.
You can explore the videos for the complete course here https://www.izenbridge.com/pmp/online-course/
The Project Management Professional (PMP) is a registered mark of the Project Management Institute, Inc.
PMBOK is a registered mark of the Project Management Institute, Inc.
Materials in this video are based on the text , A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017.
The PMI Registered Education Provider logo is a registered mark of the Project Management Institute, Inc.
#pmptraining #pmpexam #pmpvideos
Видео PMBOK® Guide : Perform Integrated Change Control Change Request Flow канала iZenBridge Consultancy Pvt Ltd
This video helps us in visualizing how to change request flows among various processes.
What is a Change Request? It is a tool for a change in the established plan or project document. So we should have a plan in place before we raise a change request.
Initiating and planning group has nothing to do with Change Request. These process groups don’t take change request as input & most of the time not as output (Procurement planning being an exception).
Executing and Monitoring & Control process groups deal with changes. In this video, you will see how the change request gets generated at various places.
In Executing Process Group you may or may not realize Change Requests. Change Requests goes directly to Integrated Change Control for further action. In case you don’t realize any change then the output is Work Performance Data (WPD), which go to the respective Knowledge Area Controlling Process. Here WPD can either generate another change requests or Work Performance Information (WPI). In the case of WPI as an output, it goes to Monitoring & Control where there are 2 possibilities, one is change request being generated, else Work Performance Report is generated. In the case of Change Request, it goes to “Approve/Reject/Deferred.”
Once a change request is received, the project team should not act on it immediately. They should first do impact analysis, it is then sent to respective stakeholder for decision making followed by a decision on the change requests. CRs can be approved, reject or deferred. Then these changes are logged in ChangeLog, a repository of detail of all the changes.
Then based on the changelog update, the project management plan is updated followed by communicating it to respective stakeholders.
You can explore the videos for the complete course here https://www.izenbridge.com/pmp/online-course/
The Project Management Professional (PMP) is a registered mark of the Project Management Institute, Inc.
PMBOK is a registered mark of the Project Management Institute, Inc.
Materials in this video are based on the text , A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017.
The PMI Registered Education Provider logo is a registered mark of the Project Management Institute, Inc.
#pmptraining #pmpexam #pmpvideos
Видео PMBOK® Guide : Perform Integrated Change Control Change Request Flow канала iZenBridge Consultancy Pvt Ltd
Показать
Комментарии отсутствуют
Информация о видео
19 июня 2019 г. 16:11:26
00:08:43
Другие видео канала
PMP training videos - Develop Project Charter (2021) - Video 1PMP Exam Questions on Hybrid Project Life Cycles | PMP® Exam QuestionsPMP training - Perform Integrated Change Control (2021) - Video 6PMBOK® Guide : Plan Risk Responses Strategies for ThreatsProject Management Professional (PMP)® Exam FAQs : To Complete Performance Index (TCPI) | iZenBridgePMBOK 6: Direct and Manage Project Work -Change RequestProject Management Process Group (PMBOK® Guide)What is agile? :Part 1 | iZenBridgeCHANGE MANAGEMENT | PERFORM INTEGRATED CHANGE CONTROL 2021 | PMP TRAINING VIDEO | PMBOK 6TH EDITIONPMBOK® Guide : What are the Project Management Knowledge Areas?4.6 Perform Integrated Change Control | PMBOK6 | PMP® Training | PMP® CertificationProject Management Professional (PMP)® | 7 Basic Quality Tools | Project Quality Management | PMBOK®PMBOK Guide CHANGE REQUESTS DATAFLOW - PMP EXAM PREPChange Request (CR) and Change Control Board (CCB)The Philosophy Behind S-CurvesPMP SITUATIONAL QUESTIONS (2021) | Integration Management - PMBOK | PMP Exam Questions and AnswersPMBOK® Guide: Plan Risk Responses Strategies for opportunitiesWhat is EARNED VALUE MANAGEMENT (EVM) in Project Cost Management (2021)? PMP Training Videos | PMBOKProject Management Professional (PMP)® | Plan Risk Responses | Project Risk ManagementProject Management Professional (PMP)® | Direct & Manage work | Project Integration Management