TAGUM CITY FLYOVER Project Update 2021
Tagum City Flyover Project is set to be opened by the last quarter of 2021.
The multi-billion pesos Tagum City Flyover project, the biggest flyover so far in Mindanao, is already 84% completed, and set to be opened to vehicular traffic by the last quarter of this year 2021, according to Department of Public Works and Highways (DPWH) XI Public Affairs and Information Officer Dean Ortiz.
The massive flyover project will help address traffic problems in Tagum City, with an estimated population of more than 260,000 according to the 2015 census of the Philippine Statistics Authority.
The construction of the flyover commenced in 2017. Phase 1 of the project covers Annette’s Chicken House to the PSBank branch in the city that involved foundation works for the structural footings and columns. It has a budget of P300 million and constructed by Ulticon Builders Inc.
Phase 2 of the project is the superstructure's elevated section, the Flyover will be finished this year, with the complete flyover spanning 1 kilometer from Car Asia towards CAP Building.
Tagum City is going the extra mile to cement itself as the next Highly Urbanized City (HUC) in Mindanao with the proposed P500-Million Tagum Stadium and Coliseum Project set to be the crowing glory of the city's progress.
Also in the pipeline is the proposed Tagum Intermodal Terminal which will sit in a 2-hectare lot in Barangay Madaum which was donated by Hijo Resources Corporation's to the City Government of Tagum.
Meanwhile, the DPWH XI completed and delivered the P76-Million Panabo Flyover Project also in the province of Davao del Norte and was opened to vehicular traffic last February 2020. The flyover was constructed using "prefabricated modular steel technology" from Matiere S.A.S., which was provided by the French Government through an assistance program. The said project which has a length of 320 m indeed helped ease traffic congestion in the city of Panabo in almost a year of operation.
tagum flyover project,
tagum city flyover project,
tagum flyover update,
tagum city flyover,
tagum city flyover update
Видео TAGUM CITY FLYOVER Project Update 2021 канала Enhinyeronggala VLOGS
The multi-billion pesos Tagum City Flyover project, the biggest flyover so far in Mindanao, is already 84% completed, and set to be opened to vehicular traffic by the last quarter of this year 2021, according to Department of Public Works and Highways (DPWH) XI Public Affairs and Information Officer Dean Ortiz.
The massive flyover project will help address traffic problems in Tagum City, with an estimated population of more than 260,000 according to the 2015 census of the Philippine Statistics Authority.
The construction of the flyover commenced in 2017. Phase 1 of the project covers Annette’s Chicken House to the PSBank branch in the city that involved foundation works for the structural footings and columns. It has a budget of P300 million and constructed by Ulticon Builders Inc.
Phase 2 of the project is the superstructure's elevated section, the Flyover will be finished this year, with the complete flyover spanning 1 kilometer from Car Asia towards CAP Building.
Tagum City is going the extra mile to cement itself as the next Highly Urbanized City (HUC) in Mindanao with the proposed P500-Million Tagum Stadium and Coliseum Project set to be the crowing glory of the city's progress.
Also in the pipeline is the proposed Tagum Intermodal Terminal which will sit in a 2-hectare lot in Barangay Madaum which was donated by Hijo Resources Corporation's to the City Government of Tagum.
Meanwhile, the DPWH XI completed and delivered the P76-Million Panabo Flyover Project also in the province of Davao del Norte and was opened to vehicular traffic last February 2020. The flyover was constructed using "prefabricated modular steel technology" from Matiere S.A.S., which was provided by the French Government through an assistance program. The said project which has a length of 320 m indeed helped ease traffic congestion in the city of Panabo in almost a year of operation.
tagum flyover project,
tagum city flyover project,
tagum flyover update,
tagum city flyover,
tagum city flyover update
Видео TAGUM CITY FLYOVER Project Update 2021 канала Enhinyeronggala VLOGS
Показать
Комментарии отсутствуют
Информация о видео
Другие видео канала
![10 GOVERNMENT PROJECTS IN MINDANAO l THIS IS NOT A MONETIZED VIDEO](https://i.ytimg.com/vi/wR6hk8vlkwk/default.jpg)
![](https://i.ytimg.com/vi/5Kir9coPlbc/default.jpg)
![DAANG HARI Update! Tagaytay City Tour 2019 Part 1. Most Visited Places in Tagaytay City.](https://i.ytimg.com/vi/OqP65iK7HDA/default.jpg)
![Apo agua,part 2 ito ang water dam sa davao city, supply ito sa davao city panabo at tagum city.](https://i.ytimg.com/vi/PCNV0mulEX0/default.jpg)
![CLLEX / Central Luzon Link Expressway update as of February 2021](https://i.ytimg.com/vi/PkITnNg9ZD4/default.jpg)
![4K Driving Greenhills - Batasan Hills | San Juan - Quezon City Ortigas Ave EDSA Commonwealth Manila](https://i.ytimg.com/vi/11BQBCwYxXw/default.jpg)
![COASTAL ROAD BAGO APLAYA-TALOMO DRONE SHOT DJI SPARK TATAK DU3O👌👍😍 OKEEEY KEEEYOOO😅🤩](https://i.ytimg.com/vi/xT3c42_DTR8/default.jpg)
![19 min only from Buendia to Balintawak. Metro Manila Skyway Stage 3 is open na. Lets go for a ride](https://i.ytimg.com/vi/mJCZ0oevv0w/default.jpg)
![ANG GANDA NA! SKYWAY STAGE 3 PROJECT UPDATE! NOVEMBER 07, 2020! SIGHTSEEING TOUR!](https://i.ytimg.com/vi/h1_Uunr7QLA/default.jpg)
![TAXI BOAT, SAKYAN NATIN - 10-KM CAVITE LAGUNA EXPRESSWAY, BINUKSAN NA! NOVEMBER 2019 UPDATE.](https://i.ytimg.com/vi/CqInSylMxQA/default.jpg)
![Hometown Ride │ Padada Davao del Sur │ Yamaha MIO i125](https://i.ytimg.com/vi/IJqYfsjE7jM/default.jpg)
![FILIPINO PASALUBONG SURPRISE - Gift Shopping Day In Tagum City (Davao, Mindanao)](https://i.ytimg.com/vi/qr6kAN3wOEY/default.jpg)
![Inter Island Bridges Explained - BUILD! BUILD! BUILD!](https://i.ytimg.com/vi/qpGLy_EsAeo/default.jpg)
![Update of the Biggest coliseum in the Bicol Region | Sorsogon Sport Complex](https://i.ytimg.com/vi/nzFL39cADKM/default.jpg)
![Philippine Arena Truss Grid](https://i.ytimg.com/vi/1k5lcwSySqk/default.jpg)
![TUGANAY-CARMEN DAVAO DEL NORTE PHILIPPINES](https://i.ytimg.com/vi/llLpqVlLWo0/default.jpg)
![ROAD TRIP UPDATE! TOUR SIGHTSEEING.. QUEZON CITY--ORTIGAS EAST, PASIG CITY](https://i.ytimg.com/vi/3xh8Ewkl-SQ/default.jpg)
![China's longest underwater highway tunnel opens](https://i.ytimg.com/vi/rRQ7gLdRVX8/default.jpg)
![Mindanao region build build build Projects.](https://i.ytimg.com/vi/Rh_14pkzTgU/default.jpg)
![The Metro Manila Subway - Update 1](https://i.ytimg.com/vi/K5J-atOtgM4/default.jpg)