Create a 7 Day Work Week in Microsoft Project | Dora Tarver

Learn how to create a seven day work week in Microsoft project. By default, a work week is 5 days but you can modify the days.

In this example, we add test tasks and test resource names. Even though this is an older version of Microsoft Project the concept is similar in newer versions. :)

When you navigate to "Change Working Time" and select the "standard" calendar, which is the default you will see that Saturday and Sunday appear greyed out.

You can edit the standard calendar or create a new calendar. Go to minute 1:52 for details. When you click on the details button you will see how to change the working time for any day of the week.

If you liked this video then consider these Project Management Tools: https://18b21n-nx78z9xainkt8mjyhs3.hop.clickbank.net/?tid=DTARVER_YOUTUBE
😎 Don't Miss this 👇 Recommended Tutorial:
How to Create a Master Schedule with MS Project: http://youtu.be/DvJIZ7lCEDw
Simple Steps for Launching your Schedule: https://youtu.be/q5TR5giMzAM
The baseline in your project schedule: https://youtu.be/jwOcWibswCI

Please like this video and subscribe!

PLEASE WATCH AND SHARE TO BLESS OTHERS.

Connect with Successful Project Management Resources Online:
Website: http://e-ProjectManagers.com
Connect on Facebook: https://www.facebook.com/dora.tarver
Follow on Twitter: https://twitter.com/dora_tarver

Thanks

Видео Create a 7 Day Work Week in Microsoft Project | Dora Tarver канала Relax and Revive with Dora
Показать
Комментарии отсутствуют
Введите заголовок:

Введите адрес ссылки:

Введите адрес видео с YouTube:

Зарегистрируйтесь или войдите с
Информация о видео
27 января 2019 г. 23:11:05
00:07:34
Яндекс.Метрика