A8 motorway. Autostrada A8 Iasi - Targu Neamt - On this day March 19, 2021
A8 motorway. Estimated cost: 4.1 billion euros.
Today, 19.03.2021, the evaluation process was completed and the communication of the result of the contract award procedure was issued, having as object “Completion / Revision / Update of Feasibility Study, and elaboration of technical project for the objective“ Targu-Neamt - Iasi - Ungheni Highway ”” .
The winning bidder is SC CONSITRANS, with the price of 58830448 Lei without VAT and a total score of 96 points, of which 40 points for the financial component and 56 points for the technical component.
The duration of the design services is as follows:
12 months for conducting the Feasibility Study;
5 months for the realization of the Project for the Authorization of the Execution of the Construction Works and the obtaining of the Construction Authorization;
5 months for the realization of the Technical Execution Project;
In the following period, after fulfilling the legal terms regarding the formulation of the appeals in accordance with the provisions of Law no. 101/2016, as well as after resolving any appeals / complaints made during the award procedure, the winning bidder will be invited to the headquarters of the National Highway Company to sign the contract, once the approval process is completed.
Translated titles:
Autostrada A8. Autostrada A8 Iași-Târgu Neamț-În această zi 19 martie 2021
Видео A8 motorway. Autostrada A8 Iasi - Targu Neamt - On this day March 19, 2021 канала On this Day
Today, 19.03.2021, the evaluation process was completed and the communication of the result of the contract award procedure was issued, having as object “Completion / Revision / Update of Feasibility Study, and elaboration of technical project for the objective“ Targu-Neamt - Iasi - Ungheni Highway ”” .
The winning bidder is SC CONSITRANS, with the price of 58830448 Lei without VAT and a total score of 96 points, of which 40 points for the financial component and 56 points for the technical component.
The duration of the design services is as follows:
12 months for conducting the Feasibility Study;
5 months for the realization of the Project for the Authorization of the Execution of the Construction Works and the obtaining of the Construction Authorization;
5 months for the realization of the Technical Execution Project;
In the following period, after fulfilling the legal terms regarding the formulation of the appeals in accordance with the provisions of Law no. 101/2016, as well as after resolving any appeals / complaints made during the award procedure, the winning bidder will be invited to the headquarters of the National Highway Company to sign the contract, once the approval process is completed.
Translated titles:
Autostrada A8. Autostrada A8 Iași-Târgu Neamț-În această zi 19 martie 2021
Видео A8 motorway. Autostrada A8 Iasi - Targu Neamt - On this day March 19, 2021 канала On this Day
Показать
Комментарии отсутствуют
Информация о видео
Другие видео канала
![Today was signed the design contract for the A8 HIGHWAY, TÂRGU NEAMȚ-IAȘI](https://i.ytimg.com/vi/wqDcsl_30j8/default.jpg)
![Ploiesti - Buzau Highway 2021 (Autostrada Ploiesti - Buzau A7), a 3D projection - On this day](https://i.ytimg.com/vi/c1dMPZt5ZCg/default.jpg)
![Asfaltari Autostrada A3 Târgu Mureș - Ungheni, 19.05.2021](https://i.ytimg.com/vi/2ILrFxSEhGE/default.jpg)
![Drum expres DX12 Craiova Pitesti | Tronson 2 | DN65-DN64 Slatina 19.05.2021](https://i.ytimg.com/vi/9zA5ZI5qq0A/default.jpg)
![Valea Oltului - portiunea pe unde va trece Autostrada A1 - Sibiu Pitesti - Lot 2](https://i.ytimg.com/vi/43aV2hYr7E4/default.jpg)
![Autostrada A10 Sebes Turda, lot 1, nodul rutier Sebes, conexiunea cu A1, 110521](https://i.ytimg.com/vi/IFS3-NIp6m0/default.jpg)
![Tokyo Has Built The World's Best Subway](https://i.ytimg.com/vi/FFpG3yf3Rxk/default.jpg)
![Descărcare Tramvai Siemens Imperio By Astra Arad Tram/Straßenbahn Unloading in Oradea - 06 May 2021](https://i.ytimg.com/vi/huKDaAz-oHE/default.jpg)
![Podul suspendat peste Dunare (in constructie) | Bridge over Danube (under construction) 29.05.2021](https://i.ytimg.com/vi/3Tjwa-JH8Ok/default.jpg)
![West Of England Steam Engine Society Road Run Up Engine Hill](https://i.ytimg.com/vi/H-tDRXFDJ94/default.jpg)
![Autostrada de Centură București: A0 Sud Lot 2 [COMPLET] - 1 mai 2021](https://i.ytimg.com/vi/cxBerJ0BU4c/default.jpg)
![Apel pentru Autostrada Unirii. Asociație Civică: Două tronsoane pot fi făcute cu bani europeni](https://i.ytimg.com/vi/fCI39yP5Nxo/default.jpg)
![Autostrada prin munte in Serbia spre Grecia](https://i.ytimg.com/vi/ZCcvgej7Tmc/default.jpg)
![Autostrada A3 Nadaselu (CJ) Zimbor (SJ) | Lucrari zona Nadaselu Sanpaul Zimbor 22.05.2021](https://i.ytimg.com/vi/yY3B1pBod4E/default.jpg)
![Autostrada A1 Sibiu Pitești lot1 Sibiu Boita 26.05.2021 - lot complet](https://i.ytimg.com/vi/4QQY7HQsljw/default.jpg)
![Mai mulți oameni și-au manifestat nemulțumirea că A8 nu este considerat un proiect prioritar](https://i.ytimg.com/vi/NYIG84DbgAk/default.jpg)
![Varianta de ocolire Bacau | DN15-DN2 bratul nordic | stadiu lucrari 10.05.2021](https://i.ytimg.com/vi/adyhrt9WhrM/default.jpg)
![Braila suspension Bridge 2021 plans (Podul de la Braila) construction site - On this day in History](https://i.ytimg.com/vi/xZutvgueQgo/default.jpg)
![Premieră: Drumul Expres Craiova Pitesti DX12 Tronsonul 3 UMB Valea Mare - Colonesti](https://i.ytimg.com/vi/ywBMggxBh14/default.jpg)
![Drumul Expres Craiova Pitesti DX12 Tronson 2 UMB Lot2 Pod Peste Raul Olt Si Balta Milcov 29052021](https://i.ytimg.com/vi/NuKcqdX5ioI/default.jpg)