What is the Critical Path Method? | CPM | Total Float | Free Float | Network Diagram | PMP Exam
Critical Path Analysis is a systematic approach used to find the Critical Path in the Schedule Network Diagram.
Schedule Network Diagram
The graphical representation of relationship between activities is called as Schedule Network Diagram. Precedence Diagramming Method or Activity-on-Node is the most commonly used technique for drawing Network Diagram.
Critical Path
- Critical Path is the path with the longest duration.
- Duration of the Critical Path is the minimum time needed to complete a project.
- The activities on the Critical Path have the least Total Float relative to other paths
Total Float
It is the amount of time by which the Early Start of an activity can be delayed without delaying the overall project.
Free Float
It is the amount of time by which the Early Start of an activity can be delayed without delaying the Early Start of successor activities.
This lesson addresses the following
- What is Critical Path Method?
- What is Precedence Diagramming Method?
- What is Activity-on-Node?
- What is Schedule Network Diagram?
- How to draw Schedule Network Diagram?
- How to find Critical Path?
- What is Free Float?
- What is Total Float?
- What is the difference between Free Float and Total Float?
- Critical Path Questions
- Critical Path Formulas
- Critical Path Problems
Additional Lessons
1. Fixed Price Incentive Fee Contracts: https://youtu.be/isEWkF5sOsQ
2. Firm Fixed Price Contracts: https://youtu.be/BtbTCzGiDUk
3. Cost Plus Incentive Fee Contracts: https://youtu.be/CCGxSMx1zIQ
4. Time Value of Money: https://youtu.be/jmkKo-vQZhk
5. NPV and IRR: https://youtu.be/56pjqu470Vo
6. Benefit-Cost Ratio & ROI: https://youtu.be/8mAR-Tpz_H0
7. Straight Line Depreciation: https://youtu.be/XTsP-PSRavM
8. Double Declining Balance Depreciation: https://youtu.be/7a8wl3BLzi4
9. Sum Of Years Digits Depreciation: https://youtu.be/Y6CKYJHRpJc
All the best with your PMP exam!!
#SunnySensei #PDM #CriticalPath
Видео What is the Critical Path Method? | CPM | Total Float | Free Float | Network Diagram | PMP Exam канала Sunny Sensei
Schedule Network Diagram
The graphical representation of relationship between activities is called as Schedule Network Diagram. Precedence Diagramming Method or Activity-on-Node is the most commonly used technique for drawing Network Diagram.
Critical Path
- Critical Path is the path with the longest duration.
- Duration of the Critical Path is the minimum time needed to complete a project.
- The activities on the Critical Path have the least Total Float relative to other paths
Total Float
It is the amount of time by which the Early Start of an activity can be delayed without delaying the overall project.
Free Float
It is the amount of time by which the Early Start of an activity can be delayed without delaying the Early Start of successor activities.
This lesson addresses the following
- What is Critical Path Method?
- What is Precedence Diagramming Method?
- What is Activity-on-Node?
- What is Schedule Network Diagram?
- How to draw Schedule Network Diagram?
- How to find Critical Path?
- What is Free Float?
- What is Total Float?
- What is the difference between Free Float and Total Float?
- Critical Path Questions
- Critical Path Formulas
- Critical Path Problems
Additional Lessons
1. Fixed Price Incentive Fee Contracts: https://youtu.be/isEWkF5sOsQ
2. Firm Fixed Price Contracts: https://youtu.be/BtbTCzGiDUk
3. Cost Plus Incentive Fee Contracts: https://youtu.be/CCGxSMx1zIQ
4. Time Value of Money: https://youtu.be/jmkKo-vQZhk
5. NPV and IRR: https://youtu.be/56pjqu470Vo
6. Benefit-Cost Ratio & ROI: https://youtu.be/8mAR-Tpz_H0
7. Straight Line Depreciation: https://youtu.be/XTsP-PSRavM
8. Double Declining Balance Depreciation: https://youtu.be/7a8wl3BLzi4
9. Sum Of Years Digits Depreciation: https://youtu.be/Y6CKYJHRpJc
All the best with your PMP exam!!
#SunnySensei #PDM #CriticalPath
Видео What is the Critical Path Method? | CPM | Total Float | Free Float | Network Diagram | PMP Exam канала Sunny Sensei
Показать
Комментарии отсутствуют
Информация о видео
Другие видео канала
CPM and PERTWhat is CRITICAL PATH METHOD in PROJECT MANAGEMENT 2021 | Project Scheduling | PMP New Syllabus 2021Determine Total Float & Free Float (AKA "Slack") of activities in a network diagramWhat is Net Present Value and Internal Rate of Return? | NPV | IRR | PMP ExamWhat is Earned Value Management? | EVM | CV, SV, CPI, SPI, EAC, ETC, TCPI, VAC | PMP ExamTECH-005 - Create a quick and simple Time Line (Gantt Chart) in ExcelDifficult network diagram example with lag solvedDetermine the Early Start (ES) and Early Finish (EF) of activities in a PDM network diagramPrecedence Diagramming 1 - Arrow Diagramming MethodUse forward and backward pass to determine project duration and critical pathCPM - Critical Path Method||Project Management Technique||Operations Research|| Solved ProblemOverview of Critical Path: Project Management Professional (PMP)® Exam PrepHow to Create a Schedule Network Diagram in ExcelWhat is Free Float (Free Slack) and how to calculate it in a network diagramPMP Mastering Critical Path Scheduling (Zero Method 101)Tricks for EST, EFT, LST, LFT, Total float, free float in project managementWhat is Time Value of Money? | Present Value | Future Value | PMP ExamGantt Chart Excel Tutorial - How to make a Basic Gantt Chart in Microsoft Excel 2013# 1 MS Project 2019 ● Basics in 20 Minutes ● EasyPMP Exam Questions And Answers - PMP Certification- PMP Exam Prep (2021) - Video 1