Amur GPP construction reaches 90.16% completion in early October 2023
Amur GPP process line 1 was put into commercial operation. Commercial products under design specifications were generated, including high-purity liquefied helium (99.9995%).
Loop and functional tests finished on process line 2. The unit for dehydration and removal of impurities is undergoing the commissioning preparations.
Process line 3 switched to its process mode. Commercial products under design specifications were generated. Hot commissioning is in progress at helium treatment, liquefaction and loading unit 2. Electrical works, pre-assembly and tests of pipelines are in progress at the natural gas liquid purification and gas fractionation units.
Watch our video for details about the progress on process lines 4, 5, and 6.
#AmurGPP
Видео Amur GPP construction reaches 90.16% completion in early October 2023 канала Газпром переработка Благовещенск
Loop and functional tests finished on process line 2. The unit for dehydration and removal of impurities is undergoing the commissioning preparations.
Process line 3 switched to its process mode. Commercial products under design specifications were generated. Hot commissioning is in progress at helium treatment, liquefaction and loading unit 2. Electrical works, pre-assembly and tests of pipelines are in progress at the natural gas liquid purification and gas fractionation units.
Watch our video for details about the progress on process lines 4, 5, and 6.
#AmurGPP
Видео Amur GPP construction reaches 90.16% completion in early October 2023 канала Газпром переработка Благовещенск
Показать
Комментарии отсутствуют
Информация о видео
12 октября 2023 г. 23:13:30
00:04:34
Другие видео канала
![Вести - Амурская область: В новые служебные квартиры переехали еще 250 сотрудников Амурского ГПЗ](https://i.ytimg.com/vi/7MpHJWn74WY/default.jpg)
![Вести - Амурская область: Амурский ГПЗ отгружает сжиженный гелий высочайшей степени очистки](https://i.ytimg.com/vi/m2eTA4BTsaA/default.jpg)
![Прогресс по проекту строительства Амурского ГПЗ к началу ноября 2023 года составил 90,53 %](https://i.ytimg.com/vi/FBv1OzK7y-0/default.jpg)
![Семьи сотрудников Амурского ГПЗ приняли участие в спортивном празднике](https://i.ytimg.com/vi/nF1haKIobvw/default.jpg)
![Отгрузка сжиженного гелия с Амурского ГПЗ](https://i.ytimg.com/vi/QNn31TYFd7Q/default.jpg)
![Гелий Амурского ГПЗ на празднике Дня знаний в Свободном](https://i.ytimg.com/vi/vG0oUG5Qh-E/default.jpg)
![40 сотрудников компании «Газпром переработка Благовещенск» приняли участие в марафоне «Бег к мечте»](https://i.ytimg.com/vi/56gkWi_i-rE/default.jpg)
![Прогресс по проекту строительства Амурского ГПЗ к началу июля 2023 года составил 89,18%](https://i.ytimg.com/vi/330foloFbMk/default.jpg)
![Amur GPP construction reaches 89.18% completion in early July 2023](https://i.ytimg.com/vi/daU0VIofjpc/default.jpg)
![Велопробегом отметили День молодежи России специалисты ООО «Газпром переработка Благовещенск»](https://i.ytimg.com/vi/QC9SX2pdI8E/default.jpg)
![Amur GPP construction reaches 89% completion in early June 2023](https://i.ytimg.com/vi/_J_YnIGKJMs/default.jpg)
![Прогресс по проекту строительства Амурского ГПЗ к началу июня 2023 года составил 89%](https://i.ytimg.com/vi/nwWuGZI_j9s/default.jpg)
![Ярмарки вакансий прошли Амурского ГПЗ в Самарской области](https://i.ytimg.com/vi/sha0tCmjmD8/default.jpg)
![Прогресс по проекту строительства Амурского ГПЗ к началу мая 2023 года составил 88,83%](https://i.ytimg.com/vi/m96svGaU8Uo/default.jpg)
![Amur GPP construction reaches 88.83% completion in early May 2023](https://i.ytimg.com/vi/-tu-sM_CaIM/default.jpg)
![Amur GPP construction reaches 88.6% completion in early April 2023](https://i.ytimg.com/vi/xoQVVODJ3bQ/default.jpg)
![Прогресс по проекту строительства Амурского ГПЗ к началу апреля 2023 года составил 88,6%](https://i.ytimg.com/vi/AH2IblRtcb0/default.jpg)
![Сотрудники ООО «Газпром переработка Благовещенск» представили вакансии Амурского ГПЗ в Башкортостане](https://i.ytimg.com/vi/GzH4ZWiCXsk/default.jpg)
![Штатное освещение Амурского ГПЗ](https://i.ytimg.com/vi/hvpP9OPiusc/default.jpg)
![Ярмарки вакансий ПАО Газпром в Москве и Санкт Петербурге](https://i.ytimg.com/vi/mAdc8ZXagYw/default.jpg)
![Маслопромывка оборудования на Амурском ГПЗ](https://i.ytimg.com/vi/8i81hagFeh4/default.jpg)