CALAX update as of July 2022 (complete subsection 4 3 2 and 1)
Thank you for tuning in to our Calax update for this month. There were not much movement in the recent months till the end of June. Sit back and relax as we show to you what we have observed!
Don't forget to visit our facebook page :
http://facebook.com/pinoyjoyride
Try watching the video on 4k mode - check the settings and select the higher resolution.
Warning: data intensive though
Finally some notcieable movement on some areas of CALAX. The most awaited horse stable ROW issue isnt still fully resolved. Late June up to early July was a busy one for the contractor LCAL as they have installed girders on three bridges. Unfortunately the weather is not cooperative plus the terrain is muddy and slippery. As for the other aras of CALAX, there are noticeable developments also.
Time Code:
0:00 Introduction
1:00 ROW Issues on Silang East Interchange / Horse Stable
1:53 Waterway Bridge 17
2:30 Subsection 4 alignment
3:40 Waterway Bridge 16 developments
4:15 UB 1 update
5:06 Subsection 4 Sabutan alignment
5:51 OB8 Update
6:10 OB 7 update
6:35 Waterway Bridge 15 girder installation
15:00 WB15 girder installation complete!
15:35 Subsection 3
16:25 Wb14 Girder installation
22:50 Wb14 girder installation completed
23:55 Subsection 2
25:00 IB3-A Girder installation Gen Trias
26:12 Sitio Maralas Area
27:40 Subsection 1 - Open Canal area
29:50 UB1 Malagasang development
30:40 MPT South Hub area Alapan 2a
32:21 Toclong Kawit
33:46 Photo souvenirs
34:04 Thank you for watching!
#CALAX #CaviteLagunaExpressway #MPTSouth #MPCALA #LCAL
#CMP #ECDL #DMCI #Cavite
Видео CALAX update as of July 2022 (complete subsection 4 3 2 and 1) канала dmitrivalencia
Don't forget to visit our facebook page :
http://facebook.com/pinoyjoyride
Try watching the video on 4k mode - check the settings and select the higher resolution.
Warning: data intensive though
Finally some notcieable movement on some areas of CALAX. The most awaited horse stable ROW issue isnt still fully resolved. Late June up to early July was a busy one for the contractor LCAL as they have installed girders on three bridges. Unfortunately the weather is not cooperative plus the terrain is muddy and slippery. As for the other aras of CALAX, there are noticeable developments also.
Time Code:
0:00 Introduction
1:00 ROW Issues on Silang East Interchange / Horse Stable
1:53 Waterway Bridge 17
2:30 Subsection 4 alignment
3:40 Waterway Bridge 16 developments
4:15 UB 1 update
5:06 Subsection 4 Sabutan alignment
5:51 OB8 Update
6:10 OB 7 update
6:35 Waterway Bridge 15 girder installation
15:00 WB15 girder installation complete!
15:35 Subsection 3
16:25 Wb14 Girder installation
22:50 Wb14 girder installation completed
23:55 Subsection 2
25:00 IB3-A Girder installation Gen Trias
26:12 Sitio Maralas Area
27:40 Subsection 1 - Open Canal area
29:50 UB1 Malagasang development
30:40 MPT South Hub area Alapan 2a
32:21 Toclong Kawit
33:46 Photo souvenirs
34:04 Thank you for watching!
#CALAX #CaviteLagunaExpressway #MPTSouth #MPCALA #LCAL
#CMP #ECDL #DMCI #Cavite
Видео CALAX update as of July 2022 (complete subsection 4 3 2 and 1) канала dmitrivalencia
Показать
Комментарии отсутствуют
Информация о видео
Другие видео канала
![dmitrivalencia - 2015 Christmas in Manila / Pasko sa Manila](https://i.ytimg.com/vi/3t2nrUO0vts/default.jpg)
![NLEX Connector - Dimasalang Girder Installation October 14 - 16, 2022](https://i.ytimg.com/vi/BF54URhrrx4/default.jpg)
![CALAX Kabayuhan - Horse Stable update as of December 30, 2022](https://i.ytimg.com/vi/dL2hxLZYxNg/default.jpg)
![CALAX Subsection 3 update as of December 2023 / OB 3 Bridge - Arnaldo Highway](https://i.ytimg.com/vi/1j_hrwymt28/default.jpg)
![Pinoy Joyride - Zambales to Pangasinan Joyride part 2 (Castillejos to San Marcelino)](https://i.ytimg.com/vi/zdGtxJ7oqtE/default.jpg)
![CALAX subsection 4 update as of February 2023](https://i.ytimg.com/vi/1a0DqVszbto/default.jpg)
![NLEX Connector section 1 - Espana Toll Plaza to R10 sunset drive](https://i.ytimg.com/vi/POAIVAY8_es/default.jpg)
![CALAX Special Update March 2023 subsection 4 - Kaong Underpass](https://i.ytimg.com/vi/hvHSDmzEooE/default.jpg)
![CALAX Subsection 4 - Girder Transport Compilation](https://i.ytimg.com/vi/TIpzxWTePPU/default.jpg)
![NLEX Connector - Connected till España off ramp!](https://i.ytimg.com/vi/395t1kusxKk/default.jpg)
![A day in El Nido Palawan - dmitrivalencia](https://i.ytimg.com/vi/xHZfulNeqgY/default.jpg)
![Metro Manila Skyway Stage 3 - Quirino On and Off Ramp Update as of January 2023](https://i.ytimg.com/vi/BWOceEsEu68/default.jpg)
![NAIA Expressway - Tramo Project Update as of August 2022](https://i.ytimg.com/vi/qPYgCvypqr0/default.jpg)
![NLEX Connector Steel Box Girder installation (G3) at Blumentritt Stn. - March 2, 2022](https://i.ytimg.com/vi/dVSlSweNCzA/default.jpg)
![CALAX subsection 4 month end update - May 2023 Update](https://i.ytimg.com/vi/BOXBVDuRzEY/default.jpg)
![CALAX subsection 4 update as of June 2023](https://i.ytimg.com/vi/rdBGeDMS884/default.jpg)
![NLEX Connector - What to expect once it opens](https://i.ytimg.com/vi/ydHFmEkX4bI/default.jpg)
![NLEX Connector Section 1 - overview / March 2023](https://i.ytimg.com/vi/VBr5aLw-1mk/default.jpg)
![Skyway Stage 3 Quirino Off Ramp - New toll plaza open!](https://i.ytimg.com/vi/SnepX8Yg25k/default.jpg)
![Christmas in Manila 2009! / Pasko sa Manila 2009 (Philippines)](https://i.ytimg.com/vi/F_qQCWa-PGc/default.jpg)
![Estrella - Pantaleon Bridge update as of May 2020](https://i.ytimg.com/vi/5R6uMxXEjUE/default.jpg)