CALAX update as of July 2022 (complete subsection 4 3 2 and 1)

Thank you for tuning in to our Calax update for this month. There were not much movement in the recent months till the end of June. Sit back and relax as we show to you what we have observed!
Don't forget to visit our facebook page :
http://facebook.com/pinoyjoyride

Try watching the video on 4k mode - check the settings and select the higher resolution.
Warning: data intensive though

Finally some notcieable movement on some areas of CALAX. The most awaited horse stable ROW issue isnt still fully resolved. Late June up to early July was a busy one for the contractor LCAL as they have installed girders on three bridges. Unfortunately the weather is not cooperative plus the terrain is muddy and slippery. As for the other aras of CALAX, there are noticeable developments also.
Time Code:
0:00 Introduction
1:00 ROW Issues on Silang East Interchange / Horse Stable
1:53 Waterway Bridge 17
2:30 Subsection 4 alignment
3:40 Waterway Bridge 16 developments
4:15 UB 1 update
5:06 Subsection 4 Sabutan alignment
5:51 OB8 Update
6:10 OB 7 update
6:35 Waterway Bridge 15 girder installation
15:00 WB15 girder installation complete!
15:35 Subsection 3
16:25 Wb14 Girder installation
22:50 Wb14 girder installation completed
23:55 Subsection 2
25:00 IB3-A Girder installation Gen Trias
26:12 Sitio Maralas Area
27:40 Subsection 1 - Open Canal area
29:50 UB1 Malagasang development
30:40 MPT South Hub area Alapan 2a
32:21 Toclong Kawit
33:46 Photo souvenirs
34:04 Thank you for watching!

#CALAX #CaviteLagunaExpressway #MPTSouth #MPCALA #LCAL
#CMP #ECDL #DMCI #Cavite

Видео CALAX update as of July 2022 (complete subsection 4 3 2 and 1) канала dmitrivalencia
Показать
Комментарии отсутствуют
Введите заголовок:

Введите адрес ссылки:

Введите адрес видео с YouTube:

Зарегистрируйтесь или войдите с
Информация о видео
11 июля 2022 г. 7:00:13
00:34:37
Яндекс.Метрика