What is the Earned Schedule? | Earned Value Management | EVM | PMP Exam | Formulas
Earned Schedule is an extension of the Earned Value Management or EVM. EVM, in its traditional form, has limitations. It is unable to capture the schedule performance of a project in units of time. It also fails to reflect the correct status of the project schedule after the project is completed. Earned Schedule, a recent addition to the Earned Value Management technique, helps to overcome these limitations.
This lesson addresses the following
- What are the limitations of the traditional EVM/EVA approach?
- What is the Earned Schedule?
- How does the Earned Schedule help to overcome the limitation of the EVM/EVA approach?
- Earned Schedule Questions
- Earned Schedule Formulas
- Earned Schedule Problems
Additional Lessons
1. Fixed Price Incentive Fee Contracts: https://youtu.be/isEWkF5sOsQ
2. Firm Fixed Price Contracts: https://youtu.be/BtbTCzGiDUk
3. Cost Plus Incentive Fee Contracts: https://youtu.be/CCGxSMx1zIQ
4. Time Value of Money: https://youtu.be/jmkKo-vQZhk
5. NPV and IRR: https://youtu.be/56pjqu470Vo
6. Benefit-Cost Ratio & ROI: https://youtu.be/8mAR-Tpz_H0
7. Straight Line Depreciation: https://youtu.be/XTsP-PSRavM
8. Double Declining Balance Depreciation: https://youtu.be/7a8wl3BLzi4
9. Sum Of Years Digits Depreciation: https://youtu.be/Y6CKYJHRpJc
All the best with your PMP exam!!
[Schedule Variance]
Schedule Variance and Cost Variance
Schedule Variance in Project Management
Schedule Variance Formula
Schedule Variance Calculation Example
Schedule Variance Example
Schedule Variance Graph
Schedule Variance Formula with Example
[Cost Variance]
Cost Variance Analysis
Cost Variance Project Management
Cost Variance Formula
Cost Variance and Schedule Variance
[Schedule Performance Index]
Schedule Performance Index (SPI)
Schedule Performance Index Calculator
Schedule Performance Index PMP
Schedule Performance Index Formula
Cost Performance Index and Schedule Performance Index
[Cost Performance Index]
Cost Performance Index in Project Management
Cost Performance Index Example
Cost Performance Index Calculation
[Budget At Completion]
Budget At Completion Project Management
Budget At Completion Example
Budget At Completion Formula
Budget At Completion PMP
#SunnySensei #EarnedValueAnalysis #EVA #TCPI #SPI #CPI
Видео What is the Earned Schedule? | Earned Value Management | EVM | PMP Exam | Formulas канала Sunny Sensei
This lesson addresses the following
- What are the limitations of the traditional EVM/EVA approach?
- What is the Earned Schedule?
- How does the Earned Schedule help to overcome the limitation of the EVM/EVA approach?
- Earned Schedule Questions
- Earned Schedule Formulas
- Earned Schedule Problems
Additional Lessons
1. Fixed Price Incentive Fee Contracts: https://youtu.be/isEWkF5sOsQ
2. Firm Fixed Price Contracts: https://youtu.be/BtbTCzGiDUk
3. Cost Plus Incentive Fee Contracts: https://youtu.be/CCGxSMx1zIQ
4. Time Value of Money: https://youtu.be/jmkKo-vQZhk
5. NPV and IRR: https://youtu.be/56pjqu470Vo
6. Benefit-Cost Ratio & ROI: https://youtu.be/8mAR-Tpz_H0
7. Straight Line Depreciation: https://youtu.be/XTsP-PSRavM
8. Double Declining Balance Depreciation: https://youtu.be/7a8wl3BLzi4
9. Sum Of Years Digits Depreciation: https://youtu.be/Y6CKYJHRpJc
All the best with your PMP exam!!
[Schedule Variance]
Schedule Variance and Cost Variance
Schedule Variance in Project Management
Schedule Variance Formula
Schedule Variance Calculation Example
Schedule Variance Example
Schedule Variance Graph
Schedule Variance Formula with Example
[Cost Variance]
Cost Variance Analysis
Cost Variance Project Management
Cost Variance Formula
Cost Variance and Schedule Variance
[Schedule Performance Index]
Schedule Performance Index (SPI)
Schedule Performance Index Calculator
Schedule Performance Index PMP
Schedule Performance Index Formula
Cost Performance Index and Schedule Performance Index
[Cost Performance Index]
Cost Performance Index in Project Management
Cost Performance Index Example
Cost Performance Index Calculation
[Budget At Completion]
Budget At Completion Project Management
Budget At Completion Example
Budget At Completion Formula
Budget At Completion PMP
#SunnySensei #EarnedValueAnalysis #EVA #TCPI #SPI #CPI
Видео What is the Earned Schedule? | Earned Value Management | EVM | PMP Exam | Formulas канала Sunny Sensei
Показать
Комментарии отсутствуют
Информация о видео
Другие видео канала
What is Earned Value Management? | EVM | CV, SV, CPI, SPI, EAC, ETC, TCPI, VAC | PMP ExamEarned Schedule- An improvement to EVM Scheduling MetricsEarned Value Management | EVM | PMP Questions and Answers 1 | PMP Exam PrepHow to Calculate Earned ScheduleFree Training on Earned Value Management (EVM)PMP Formulas in under 5 minutes for PMP CertificationWhat is a Fixed Price Incentive Fee Contracts? | Contract Types | FPIF | PMP Exam | PTAThe Basics of Project Cost Management - Project Management TrainingWhat Goes Into a Project Management Status ReportCalculating and Understanding Cost VariancePMP Exam CONTRACT Types SIMPLIFIED - FP, CR, T&M (PMBOK Guide)How to Deliver Effective Project Cost ManagementThe Problem(s) with Using Earned Value Management on a Project ScheduleCost Plus Incentive Fee Contracts (CPIF) - Part 2: Questions, Formulas and Solutions | PMP | PMBOKEarned Schedule - An Introductory VideoCost Performance Index and Schedule Performance Index - CPI and SPI ExampleNet Present Value Explained in Five MinutesWhat is Earned Value Management - EVM? PM in Under 5Earned Value Management Formulas in 5 Minutes!PMP Exam, Earned Value Management Full Course Part 5 - Best EVM course to Passing All EMV Questions