Metro Tunnel Construction Sequence

This short video gives and explains the sequence to construct a metro tunnel.
Prior to tunnelling a launch pit or underground station is constructed in which the tunnel boring machine can be assembled. A reception pit or station has to be constructed to a stage where the tunnel boring machine can pass through it, or be recovered, when the tunnel boring machine arrives.
The tunnel boring machine also known as a TBM, excavates the ground by the rotating head and then places precast wall segments to form rings that in turn form the tunnel walls.
Precast wall segments are transported on mine wagons through the completed tunnel to the back of the TBM.
The excavated material is transported on conveyor belts to a station and lifted to ground level by skip and crane from where it is transported off site by tipper lorries.
The tunnel fit-out comprises constructing the tunnel floor, drainage, installation of track, wall brackets, tunnel ventilation, high voltage power, signalling, communications and overhead line equipment.
Commissioning involves running trains to ensure the operational systems are functioning correctly

Видео Metro Tunnel Construction Sequence канала David Moloney
Показать
Комментарии отсутствуют
Введите заголовок:

Введите адрес ссылки:

Введите адрес видео с YouTube:

Зарегистрируйтесь или войдите с
Информация о видео
22 мая 2019 г. 16:46:25
00:03:54
Яндекс.Метрика