Phoenix Tower Chiller Replacement Project by Consolidated Crane & Rigging
Excited to share this inside look at one of Houston's biggest crane & rigging projects...check it out here!”
This chiller change-out project posed a unique set of challenges that arose from a variety of factors such as: building height of over 430', restricted size of the job site, unlevel ground conditions, and limited window to mobilize the crane, which all contributed to the complexity of the job.
It was quickly determined that no hydraulic truck crane could make these lifts. Consolidated's out of the box approach was to bring in a 660 ton crawler crane with 590' of boom and jib. With a 2 day window prior to crane arrival, Consolidated brought in over 200 tons of crushed concrete and more than 100 timber mats to build a level pad for the massive crane.
This unique crane configuration consisted of 55 truck loads and required over 1 million pounds of counterweight just to raise the boom off the ground. Delivering everything into the heart of Houston with a tight timetable was no small feat. Three assist cranes were positioned around the site to ensure seamless unloading and assembly of the crane.
Watch this video to see the end result of months of planning and hard work by the team at Consolidated.
Consolidated Crane & Rigging
6370 Long Dr, Houston, TX 77087, USA
713-641-3330
https://www.consolidatedcrane.com
Filmed and edited by Jatin Das Gupta
Music composition by Isaiah Macmenami
Видео Phoenix Tower Chiller Replacement Project by Consolidated Crane & Rigging канала Consolidated Crane & Rigging
This chiller change-out project posed a unique set of challenges that arose from a variety of factors such as: building height of over 430', restricted size of the job site, unlevel ground conditions, and limited window to mobilize the crane, which all contributed to the complexity of the job.
It was quickly determined that no hydraulic truck crane could make these lifts. Consolidated's out of the box approach was to bring in a 660 ton crawler crane with 590' of boom and jib. With a 2 day window prior to crane arrival, Consolidated brought in over 200 tons of crushed concrete and more than 100 timber mats to build a level pad for the massive crane.
This unique crane configuration consisted of 55 truck loads and required over 1 million pounds of counterweight just to raise the boom off the ground. Delivering everything into the heart of Houston with a tight timetable was no small feat. Three assist cranes were positioned around the site to ensure seamless unloading and assembly of the crane.
Watch this video to see the end result of months of planning and hard work by the team at Consolidated.
Consolidated Crane & Rigging
6370 Long Dr, Houston, TX 77087, USA
713-641-3330
https://www.consolidatedcrane.com
Filmed and edited by Jatin Das Gupta
Music composition by Isaiah Macmenami
Видео Phoenix Tower Chiller Replacement Project by Consolidated Crane & Rigging канала Consolidated Crane & Rigging
Показать
Комментарии отсутствуют
Информация о видео
8 октября 2018 г. 4:36:23
00:12:20
Другие видео канала
10 Largest and Tallest Cranes in the WorldFranz Bracht KG Entladung eines Großtrafos aus einem BinnenschiffTNT Crane & Rigging Lifting 200,000 lbs Column CapsOne day with the crew - Lifting action by a FPSO integration project in BrazilManitowoc 310001400 ton MEGA SCHWERTRANSPORT SPMT auf 64 ACHSEN BAUSTELLE EISENBAHN BRÜCKE DOKU [2] DREAM MACHINESAssemble and operate the world's largest tower crane and super giant excavatorMoh Seng Cranes | Liebherr LTM1750 - 9.1 | Luffing Jib 84m - Part 1All State Crane and Rigging - Potain MDT 219 Tower CraneFagioli - LR11350 Venice loading of 950 ton reactorsZwaartransport en hijswerkI was SHOCKED when see this dangerous heavy equipment destroy everything. Incredible excavatorsWorld's Dangerous Haulage Truck Monster Machines Operator, Heavy Equipment Biggest Machinery WorkingKomplettabbruch Dienstbahnbrücke der Internationalen Rheinregulierung Kriessern-Mäder (2020)Salvage of sunken car carrier TricolorThe Most Advanced Knuckle Boom Trucks You Have To See ▶ 150 ton all terrain truck5 Extreme Biggest Heavy Equipment Machines Working Dangerous Biggest Crane Truck Operator SkillWatch TNT's Manitowoc 18000 Lifting Another Crane Across a Canal2014 0822 Aufbau Raupenkran TEREX Superlift 3800Big Blue Documentary OSHA 30