A1 Sibiu - Pitești motorway / Sibiu - Boița section - 25% in less than six months

Work on the 13,7 kilometer long section from Sibiu to Boița, part of the A1 Sibiu - Pitești motorway in Romania, has reached 25% in less than six months from the start.

The almost 127 million euro contract, signed back in 2019 with the Austrian construction company PORR, has a deadline of three years to be completed from the moment the construction starts.

Works started at the beginning of April 2020, after 12 months for the design phase.

Video source: DRDP Brașov