One of the most important topics from the PMP® exam point of view.
We begin with an example- primary assumption of earned value is -- whatever we do in a project has some value.
"This value is the amount of work we are getting against our budgeted amount"
-The earned value calculation we use budgeted amount budget at completion
-Earned value measures the performance, schedule and time in monetary terms
Explained with the help of an example
-Earned value curve or S-Curve discussed
-What is cost variance and schedule variance
-Cost performance index and schedule performance index
The entire topic is discussed and explained with the help of an example so as to give an idea of the practical implication of the process.
Watch the full video session and drop us feedback. We would love to add more value to our video presentations with your assistance.
The Project Management Professional (PMP), PMBOK, The Agile Certified Practitioner (PMI-ACP), and The Professional in Business Analysis (PMI-PBA) is a registered mark of the Project Management Institute, Inc.
PMBOK is a registered mark of the Project Management Institute, Inc.
Materials in this video are based on the text, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017.
The PMI Registered Education Provider logo is a registered mark of the Project Management Institute, Inc.
Get PMP® certified in 45 Days with PMBOK ® Guide: https://bit.ly/37vUkrY
#PMP #iZenBridge #ProjectManagement #EarnedValue
Видео Project Management Professional (PMP)® Earned Value Management : Cost Control | iZenBridge канала iZenBridge Consultancy Pvt Ltd
Be a part of the latest discussions on PMP® Certification Training and PMP® Exam http://goo.gl/91L1cw
One of the most important topics from the PMP® exam point of view.
We begin with an example- primary assumption of earned value is -- whatever we do in a project has some value.
"This value is the amount of work we are getting against our budgeted amount"
-The earned value calculation we use budgeted amount budget at completion
-Earned value measures the performance, schedule and time in monetary terms
Explained with the help of an example
-Earned value curve or S-Curve discussed
-What is cost variance and schedule variance
-Cost performance index and schedule performance index
The entire topic is discussed and explained with the help of an example so as to give an idea of the practical implication of the process.
Watch the full video session and drop us feedback. We would love to add more value to our video presentations with your assistance.
The Project Management Professional (PMP), PMBOK, The Agile Certified Practitioner (PMI-ACP), and The Professional in Business Analysis (PMI-PBA) is a registered mark of the Project Management Institute, Inc.
PMBOK is a registered mark of the Project Management Institute, Inc.
Materials in this video are based on the text, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017.
The PMI Registered Education Provider logo is a registered mark of the Project Management Institute, Inc.
Get PMP® certified in 45 Days with PMBOK ® Guide: https://bit.ly/37vUkrY
#PMP #iZenBridge #ProjectManagement #EarnedValue
Видео Project Management Professional (PMP)® Earned Value Management : Cost Control | iZenBridge канала iZenBridge Consultancy Pvt Ltd
Показать
Комментарии отсутствуют
Информация о видео
9 июля 2013 г. 21:48:00
00:36:58
Другие видео канала
What is EARNED VALUE MANAGEMENT (EVM) in Project Cost Management (2021)? PMP Training Videos | PMBOKProject Management Professional (PMP)® Exam FAQs : Estimate At Completion (EAC) |iZenBridgePMBOK® Guide Sixth edition: Difference between Total Float & Free FloatGetting Ready for Scrum Master Interview : Everything you need to know : iZenBridgeEarned Value Management for Project Managers: EVM explained by an APM PMQ trainerPMBOK® Guide: Schedule Compression - Difference between Fast-Tracking and CrashingProject Management Professional (PMP)® | Create WBS | Project Scope ManagementProject Management Professional (PMP)® | 7 Basic Quality Tools | Project Quality Management | PMBOK®What is Earned Value Management? | EVM | CV, SV, CPI, SPI, EAC, ETC, TCPI, VAC | PMP ExamPMBOK® Guide-Sixth edition : Earned Value Management AnalysisProject Manager Interview Questions and Answers | PMP Certification Training | EdurekaProject Management Professional (PMP)® FAQs | Critical Path Method | Project Time Management |Earned value analysis worked examplePMBOK 6: Critical Path MethodEstimate Costs and Determine BudgetsProject Procurement Management - PMP Exam Mentoring Session #pmp #procurement #pmbokAgile-Estimation, Forecasting and Self Organizing - Discussion with SaketEarned Value Analysis: Worked ExampleProject Management Professional (PMP)® | Plan Stakeholder Management |Project Stakeholder Management