UER-2 : Alipur to Kanjhawala Stretch | Opening Soon | April 2025 Update #detoxtraveller

74.98 km Delhi Urban Extension Road (UER) II project is an under construction expressway (NH-344M) by NHAI which in Phase 1 will form a 38.111 km 3rd semi Ring Road within Delhi along its western boundary.

The project was envisioned in the early 2000s by DDA as part of Delhi’s 2021 Master Plan, but was handed over to NHAI in 2018 after it failed to take off due to land acquisition and financial issues. DDA will now provide viability gap funding worth Rs. 4000 crore.

UER 2’s Detailed Project Report (DPR) was created by URS Scott Wilson India – AECOM India JV. The project also features two spurs (NH-344P) to Bahadurgarh Bypass and to Barwasni Bypass in Sonipat. A 7.5 km section of UER 2 is currently under construction by J Kumar Infraprojects as part of Dwarka Expressway’s packages 1 and 2
Google Sheet - https://docs.google.com/spreadsheets/d/1t91bH2RdQ85TuGHTyb5ThR2BexmkmvrXr5pkatwNyY8/edit?usp=drivesdk
------------------------------------------------------------------------------------------------------------------------------------------------------------------
Instagram - https://www.instagram.com/detox.traveller/
Email - Mohit.detoxtraveller@gmail.com
Twitter - https://twitter.com/DetoxTravellerr
Linkedin - https://www.linkedin.com/in/detoxtraveller/
------------------------------------------------------------------------------------------------------------------------------------------------------------------
Gear that I use :-
Chest Mount - https://amzn.to/3rW9Zta
External Hard Disk - https://amzn.to/3KtlGjt
Gimbal - https://amzn.to/33RX578
Gorilla tripod - https://amzn.to/33SfK2y
Car Mobile Holder - https://amzn.to/3IpdsY2
Tripod Mount - https://amzn.to/3KsA4bP
Car Charger - https://amzn.to/3rT4dJ1
Windshield Mount - https://amzn.to/3GQjPDa
Long Tripod - https://amzn.to/3qTD5u9
Tyre inflator - https://amzn.to/3AiwVGT
Gopro9 - https://amzn.to/3tKoItU

Song: Sunbalt - Delante
Music provided by Vlog No Copyright Music.
Link: https://bit.ly/3YMWwW7
00:00 - 00:31 - Music
00:32 - 1:47 - Project Introduction 1
1:48 - 2:44 - Sonipat Spur Pending Flyover Progress
2:45 - 3:33 - Project Introduction 2
3:34 - 6:07 UER-2 Starting Point
6:08 - 6:37 - First Intersection
6:38 - 6:47 - Timelapse
6:48 - 7:05 - Alipur-Narela Road
7:06 - 7:42 - Holambi Kalan ROB
7:43 - 8:14 - Holambi Kalan MAIN ROAD
8:15 - 8:24 - Timelapse
8:25 - 8:44 - Bawana Sector 5
8:45 - 9:11 - Timelapse
9:12 - 9:27 - Sonipat Spur Starting Point
9:28 - 9:40 - Timelapse
9:41 - 10:30 - Bawana Road Crossing
10:31 - 10:56 - Timelapse
10:57 - 11:19 - Kanjhawala Road Crossing
11:20 - 11:28 - End of Package-1
11:29 - 12:02 - Video Ending