Overall progress of Amur GPP construction by early August 2022 amounted to 86%

Restoration and pre-commissioning are underway on process lines 1 and 2.

Pre-commissioning on the major equipment and internal checks of instrumentation in the control room are underway on process line 3. Tests of the foam extinguishing system, sprinkler systems, water discharge of the fire monitor and additional tests of the process pipelines for tightness have been completed at the helium treatment, liquefaction and loading unit. Pre-commissioning on Ladoga gas pumping units No. 5 and No. 6 have been completed.

Individual tests of heating, ventilation and air conditioning systems are underway in the indoor switchgear building and transformer substation on process line 4. The substation is ready to receive power.

Installation of sandwich panels and the major equipment of the control system is underway in the indoor switchgear building on process line 5.

Assembly of the steel and reinforced concrete structures and construction of the driveways and landscaping of the territory are underway on process line 6.
Commissioning of equipment has been completed at the sewage treatment facilities; industrial storm runoff is being processed and treated runoff is being supplied for own needs; processes are being tuned in order to achieve their design performance.

#AmurGPP

Видео Overall progress of Amur GPP construction by early August 2022 amounted to 86% канала Газпром переработка Благовещенск
Показать
Комментарии отсутствуют
Введите заголовок:

Введите адрес ссылки:

Введите адрес видео с YouTube:

Зарегистрируйтесь или войдите с
Информация о видео
11 августа 2022 г. 13:54:33
00:04:26
Другие видео канала
Explanation of Boiler Feed Water & Its Treatment | Engineering ChemistryExplanation of Boiler Feed Water & Its Treatment | Engineering ChemistryOverall progress of Amur GPP construction by early July 2022 amounted to 85.82%Overall progress of Amur GPP construction by early July 2022 amounted to 85.82%На 3 линии Амурского ГПЗ прошли испытания систем безопасностиНа 3 линии Амурского ГПЗ прошли испытания систем безопасностиСтроительство Амурского ГПЗ дало мощный импульс для развития Дальнего Востока. Репортаж НТВ.Строительство Амурского ГПЗ дало мощный импульс для развития Дальнего Востока. Репортаж НТВ.Общий прогресс по проекту строительства Амурского ГПЗ к началу июля 2022 года составил 85,82%Общий прогресс по проекту строительства Амурского ГПЗ к началу июля 2022 года составил 85,82%Overall progress of the Amur Gas Processing Plant construction project in April 2021 was 75.1%Overall progress of the Amur Gas Processing Plant construction project in April 2021 was 75.1%How LUXURY Rolls-Royce Cars Are Made ? (Mega Factories Video)How LUXURY Rolls-Royce Cars Are Made ? (Mega Factories Video)Construction Progress of Amur Gas Processing Plant Reaches 68.8% in October 2020Construction Progress of Amur Gas Processing Plant Reaches 68.8% in October 2020Overall progress of Amur GPP construction by early June 2022 amounted to 85.44%Overall progress of Amur GPP construction by early June 2022 amounted to 85.44%Общий прогресс по проекту строительства Амурского ГПЗ к началу августа 2022 года составил 86%Общий прогресс по проекту строительства Амурского ГПЗ к началу августа 2022 года составил 86%Общий прогресс по проекту строительства Амурского ГПЗ к началу апреля 2022 года составил 84,44%Общий прогресс по проекту строительства Амурского ГПЗ к началу апреля 2022 года составил 84,44%Incredible Airbus building & assembling process. Amazing airplane propeller manufacturing.Incredible Airbus building & assembling process. Amazing airplane propeller manufacturing.Really shot amazing super natural gas pipeline welding!Really shot amazing super natural gas pipeline welding!complete construction of RCC -DESIGNcomplete construction of RCC -DESIGNThe journey of natural gasThe journey of natural gasA Drill Pipe ConnectionA Drill Pipe ConnectionAmazing Production Process with Modern Machines and Skilful WorkersAmazing Production Process with Modern Machines and Skilful WorkersНа Амурском ГПЗ проводятся пусконаладочные работы на второй установке производства товарного гелияНа Амурском ГПЗ проводятся пусконаладочные работы на второй установке производства товарного гелияBad ConnectionBad ConnectionMost Satisfying Factory Machines and Ingenious ToolsMost Satisfying Factory Machines and Ingenious Tools
Яндекс.Метрика