Production from foam concrete blocks (CLC blocks) on equipment from company "GRIVAS" (Ukraine)

Line for the production of foam concrete blocks (blocks of cellular concrete) from the trade mark GRIVAS.

The video shows production line of foam concrete blocks conveyor manufacturing method with automatic dosage components.

This video clip shows process of loading of cement from cement truck in the silos (storage) of cement and a further loading of cement screw conveyor from the silo into the batcher.

Feeding of sand carried out. by using belt feeder of the storage hopper to the vibrating screen and further. loading sifted sand along a conveyor belt (L -12 m) into the batcher.

To implement automatic dosing, all batcher are mounted on load cells and control the dosage of components (cement, sand and water) is carried out by using weighting controller.

After dosing, are downloading all components in mixer for foam concrete production in the sequence, water - cement - sand, then using a foam generator is fed to the mixer foam in the right quantity.

When the mixer is loaded with all components, begins the process of mixing. 3-4 minutes is a ready-foamed concrete, which merges into the molds for the production of foam concrete.

Metal sides forms are installed on a pallet-trolley that move on rails by using electromechanical pusher or manually.

After filling out the form by foam concrete, an array from foam concrete or aerated concrete is fed on the cutting plot, which produces cutting foam concrete blocks by using complex for cutting cellular concrete URMP-2P (belt multiedger). Cutting of the array can be made into blocks with a multiplicity of 50 mm.

Видео Production from foam concrete blocks (CLC blocks) on equipment from company "GRIVAS" (Ukraine) канала GRIVAS Ukraine
Показать
Комментарии отсутствуют
Введите заголовок:

Введите адрес ссылки:

Введите адрес видео с YouTube:

Зарегистрируйтесь или войдите с
Информация о видео
3 марта 2014 г. 17:24:42
00:13:56
Яндекс.Метрика