NLEX SLEX CONNECTOR UPDATE AS OF FEBRUARY 3, 2022
THE North Luzon Expressway-South Luzon Expressway (NLEX-SLEX) connector road project is targeted to open before the year ends, Department of Public Works and Highways (DPWH) Secretary Mark Villar said.
“Ang project po ay 40 percent ang physical accomplishment at 85 percent ang site possession ng ating right of way,” (The physical accomplishment of the project is now 40 percent while the site possession of right of way is 85 percent),” said Villar during inspection on Tuesday.
Villar added they are targeting to deliver the project up to España before end 2021.
The project will be linked to the Skyway Stage 3, mostly traversing the Philippine National Railways rail track.
It includes two interchanges located at C3 Road or 5th Avenue, Caloocan and España Avenue, Manila.
The DPWH secretary also said the connector will decongest traffic in EDSA and will provide route for trucks coming from ports.
“Magiging bypass ito ng EDSA. So, kapag nasa Skyway ka, pwede kang um-exit at dire-diretso ito hanggang Harbor-Link, at magkakaroon din ng exit ramp sa may España,” he said.
The expressway will provide trucks with 24/7 alternative routes, resolve truck-ban problems, and better access to Manila Ports (North Harbor) and Airports (NAIA and Clark).
Once completed, the expressway is seen to reduce travel time from SLEX to NLEX from two hours to just 20 minutes. Travel time from Clark to Calamba will be cut to one hour and 40 minutes from the previous three hours.
DPWH said the project will benefit at least 35,000 motorists per day.
#nlex
#nlexslexconnector
#nlexslexconnectorproject
#mptc
#mptnorth
Видео NLEX SLEX CONNECTOR UPDATE AS OF FEBRUARY 3, 2022 канала UPDATED EVERYDAY
“Ang project po ay 40 percent ang physical accomplishment at 85 percent ang site possession ng ating right of way,” (The physical accomplishment of the project is now 40 percent while the site possession of right of way is 85 percent),” said Villar during inspection on Tuesday.
Villar added they are targeting to deliver the project up to España before end 2021.
The project will be linked to the Skyway Stage 3, mostly traversing the Philippine National Railways rail track.
It includes two interchanges located at C3 Road or 5th Avenue, Caloocan and España Avenue, Manila.
The DPWH secretary also said the connector will decongest traffic in EDSA and will provide route for trucks coming from ports.
“Magiging bypass ito ng EDSA. So, kapag nasa Skyway ka, pwede kang um-exit at dire-diretso ito hanggang Harbor-Link, at magkakaroon din ng exit ramp sa may España,” he said.
The expressway will provide trucks with 24/7 alternative routes, resolve truck-ban problems, and better access to Manila Ports (North Harbor) and Airports (NAIA and Clark).
Once completed, the expressway is seen to reduce travel time from SLEX to NLEX from two hours to just 20 minutes. Travel time from Clark to Calamba will be cut to one hour and 40 minutes from the previous three hours.
DPWH said the project will benefit at least 35,000 motorists per day.
#nlex
#nlexslexconnector
#nlexslexconnectorproject
#mptc
#mptnorth
Видео NLEX SLEX CONNECTOR UPDATE AS OF FEBRUARY 3, 2022 канала UPDATED EVERYDAY
Показать
Комментарии отсутствуют
Информация о видео
Другие видео канала
![MRT-7 Continuous 4K60 Drone Shot From Regalado to SM North | As Of 02/05/2022](https://i.ytimg.com/vi/CMUif-VZOc8/default.jpg)
![BATANGAS - QUEZON PROVINCE EXPRESSWAY ! MABILIS ITO ! TIAONG , LAGUNA INTERCHANGE UPDATE](https://i.ytimg.com/vi/4Js24O_mOGw/default.jpg)
![AERIAL FOOTAGE NLEX-SLEX CONNECTOR PROJECT UPDATE ALONG ANTIPOLO BETWEEN ESPAÑA BLVD & G. TUAZON ST](https://i.ytimg.com/vi/McczaS3aobo/default.jpg)
![METRO MANILA SUBWAY UPDATE | TBM Shaft, PRI Bldg., Depot](https://i.ytimg.com/vi/-zawm-ABRW0/default.jpg)
![2021 NLEX Accomplishments](https://i.ytimg.com/vi/jxunjlrw094/default.jpg)
![Metro Cebu Expressway | 73.75 Kilometer High Standard Arterial Road | Segment 3 Update](https://i.ytimg.com/vi/SMTyDycXE28/default.jpg)
![ANG LAWAK NA ! Navotas Boulevard Business Park - The Southern Gateway to Bulacan Airport |](https://i.ytimg.com/vi/tRTGMVbZWVk/default.jpg)
![Wow! demolition na naman!NLEX-SLEX CONNECTOR UPDATE(February 01,2022)|buildbuildbuild|RickzCalTV](https://i.ytimg.com/vi/LjZ1LmZc11U/default.jpg)
![2022 NLEX Infrastructure Projecs](https://i.ytimg.com/vi/aUF3scGfsu0/default.jpg)
![illegal STRUCTURES ! SUNOD SUNOD DINIMOLISH ! NLEX - SLEX CONNECTOR | ESPAÑA MANILA UPDATE](https://i.ytimg.com/vi/z4S2_kMt3Vg/default.jpg)
![8KMS AERIAL VIEW ANG HABA! 23 BILLION PROJECT NLEX SLEX CONNECTOR FROM HARBOR LINK TO SKYWAY STAGE 3](https://i.ytimg.com/vi/e_QGkXn8aNw/default.jpg)
![NLEX-SLEX Connector Road Project! Blumentritt Update Today [Feb. 02, 2022]](https://i.ytimg.com/vi/4SNtsgdlFEI/default.jpg)
![NEW MANILA INTERNATIONAL AIRPORT ! Preparatory in Progress ! Ang Lawak nito ! TALIPTIP , BULACAN](https://i.ytimg.com/vi/vJ7H-eQNS08/default.jpg)
![Lalong pinaganda pa Skyway stage 3 update 2022.#dandriveyt #skywaystage3 #buildbuildbuild #vlogs](https://i.ytimg.com/vi/bkOBKDx_ILE/default.jpg)
![mrt line 7 QC MEMORIAL CIRCLE STATION update||may tagusan pala dito||2-4-22||RUEL'S TV](https://i.ytimg.com/vi/WXrSArYsfLY/default.jpg)
![ANG PIER NGAYON MANILA PORT GANITO NA! DITO DIN PO PALA ANG WEST EXTENSION OF LRT2 PIER 4 TUTUBAN](https://i.ytimg.com/vi/j3KiLDbDp0o/default.jpg)
![NLEX-SLEX CONNECTOR UPDATE | COPING BEAM ITINATAYO SA KAHABAAN NG ANTIPOLO ST. #nlexslexconnector](https://i.ytimg.com/vi/h1jdrJFFFmE/default.jpg)
![NLEX further boosts customer service in 2022](https://i.ytimg.com/vi/-TNRBKbqBpE/default.jpg)
![Wow!dami agad scaffolding|NLEX-SLEX CONNECTOR UPDATE(February 03,2022)|buildbuildbuild|RickzCalTV](https://i.ytimg.com/vi/499fsnUPOVM/default.jpg)
![skyway stage 3 sgt revira cor A bonifacio c3 connector update|2-3-22||RUEL'S TV](https://i.ytimg.com/vi/8ErupPTL910/default.jpg)