03_01_P1 Basics of Stopwatch Time Study
Stopwatch time study
Work measurement
Standard time
00:01 Introduction
04:14 Applications of time study
08:18 Types of stopwatch
09:32 Steps of stop watch time study
11:50 Step 1: defining the task to be studied
15:17 Step 2: Dividing the job into elements
20:05 Step3: Deciding how many times to measure the task
30:13 Step 4 and 5: Performance rating and average observed time
38:35 Step 6 and 7: Finding the normal time
40:57 Finding the allowances and standard time
48:10 Time study observation sheet
Видео 03_01_P1 Basics of Stopwatch Time Study канала Industrial Engineering and Manufacturing
Work measurement
Standard time
00:01 Introduction
04:14 Applications of time study
08:18 Types of stopwatch
09:32 Steps of stop watch time study
11:50 Step 1: defining the task to be studied
15:17 Step 2: Dividing the job into elements
20:05 Step3: Deciding how many times to measure the task
30:13 Step 4 and 5: Performance rating and average observed time
38:35 Step 6 and 7: Finding the normal time
40:57 Finding the allowances and standard time
48:10 Time study observation sheet
Видео 03_01_P1 Basics of Stopwatch Time Study канала Industrial Engineering and Manufacturing
Показать
Комментарии отсутствуют
Информация о видео
8 ноября 2022 г. 15:13:15
00:50:32
Другие видео канала
![01_02_P2 Locating a Part in Fixtures and Jigs Through a Hole](https://i.ytimg.com/vi/VHoG7P3LFsI/default.jpg)
![04_02_P4 Taylor's Theory To Design Snap Gauges (without wear allowance)](https://i.ytimg.com/vi/anF1JVubwNk/default.jpg)
![02_03_P1 Milling Cutters](https://i.ytimg.com/vi/_KEcZTvMges/default.jpg)
![04_03_P6 Solving an MRP Matrix with Multiple BOMs](https://i.ytimg.com/vi/y_CkZIq87-A/default.jpg)
![01_04_P3 Liner (Master) Bushings and Renewable Bushings](https://i.ytimg.com/vi/yyw6lINob84/default.jpg)
![02_04_P10 Bucketless Material Requirements Panning (MRP)](https://i.ytimg.com/vi/pcDh1lkaoJU/default.jpg)
![02_03_P2-2 Bill of Material: Low Level Code in a Multiple Level BOM](https://i.ytimg.com/vi/GouWNPZbKe0/default.jpg)
![03_03_P4 Simple Exponential Smoothing Using Excel](https://i.ytimg.com/vi/-_kKCl-S6kM/default.jpg)
![02_03_P6 Engineering Change Management Using Bill of Material (BOM)](https://i.ytimg.com/vi/2fimfjxrbCo/default.jpg)
![00_03_P2 Limits and Tolerances](https://i.ytimg.com/vi/akWvmOU7iNU/default.jpg)
![00_02 QUIZ](https://i.ytimg.com/vi/aviJg2Bodmw/default.jpg)
![01_05_A Work-Related Musculoskeletal Disorders (WMSDs)](https://i.ytimg.com/vi/Ks8QpPvW-sw/default.jpg)
![03_01_P4-3 Priority Rules in a Job Shop: Example 4 (CR)](https://i.ytimg.com/vi/tfqL7j2192w/default.jpg)
![03_03_P5 Finding Production Time in an Assembly Line](https://i.ytimg.com/vi/snBP_IcJ6U8/default.jpg)
![03_01_P1 Basics of Job Shop or Jobbing Process](https://i.ytimg.com/vi/_ujtxU_2sgo/default.jpg)
![01_01_P1 The Need for Fixtures and Jigs in Machining](https://i.ytimg.com/vi/oFP9PDsVvaY/default.jpg)
![03_03_P3 The Position of the Layout Line and Bend Lines in Sheet Metal Bending](https://i.ytimg.com/vi/Zvfmu164eQ4/default.jpg)
![01_03_P5 Cam Action Clamps](https://i.ytimg.com/vi/enDwqFJ9KEg/default.jpg)
![03_04_P7 Reverse Drawing Process](https://i.ytimg.com/vi/Yp-o6rRwHQg/default.jpg)
![03_03_P3 Using Takt Time to Make Workstations in an Assembly Line: Example 1 Part 2](https://i.ytimg.com/vi/8Yyyhf-Pdbo/default.jpg)
![02_01_P1 Sales and Operations Planning (S & OP) Basics](https://i.ytimg.com/vi/Ornu5tbbXB4/default.jpg)