NavoiyAzot Fertilizer Plant, Uzbekistan

The project location is Navoi, Republic of Uzbekistan;
The equipment delivery period is September 2017 – December 2018;
The volume of transported equipment – 7,980 tons, 35,800 cubic meters.

Limiting equipment:
- Ammonia synthesis column 422 tons, 27,780 x 4,290 x 5000 mm;
- Auxiliary boiler 240 tons, 12,700 x 8,700 x 10,720 mm;
- CO2 absorber 360 tons, 49 080 x 6 100 x 6 760 mm;
- CO2 evaporator 269 tons, 52 540 x 7 100 x 7 490 mm.

The company Barrus Projects completed the delivery of equipment for the complex under construction. Transportation began in September 2017 and lasted until the end of 2018. The total volume of the transported equipment amounted to 7,980 tons, 35,800 cubic meters.
-------------------
Завершен проект доставки оборудования для АО «НавоиАзот»

Местонахождение проекта – г. Навои, Республика Узбекистан;
Период доставки оборудования – сентябрь 2017 – декабрь 2018;
Объем перевозимого оборудования – 7 980 тонн, 35 800 куб. метров.

Лимитирующее оборудование:
- Колонна синтеза аммиака 422 тонны, 27 780 х 4 290 х 5000 мм;
- Вспомогательный бойлер 240 тонн, 12 700 х 8 700 х 10 720 мм;
- СО2 абсорбер 360 тонн, 49 080 х 6 100 х 6 760 мм;
- СО2 выпариватель 269 тонн, 52 540 х 7 100 х 7 490 мм.

Компания «Баррус. Проектная логистика» выполнила доставку оборудования для строящегося комплекса. Транспортировка началась в сентябре 2017 г. и продолжалась до конца 2018 года. Общий объем перевезенного оборудования составил 7 980 тонн, 35 800 куб. метров.

Видео NavoiyAzot Fertilizer Plant, Uzbekistan канала Barrus Projects
Показать
Комментарии отсутствуют
Введите заголовок:

Введите адрес ссылки:

Введите адрес видео с YouTube:

Зарегистрируйтесь или войдите с
Информация о видео
1 февраля 2019 г. 0:41:20
00:08:53
Яндекс.Метрика