The Twenty Sixth Work Week of St Peter Church Expansion Project August 22 thru 26, 2016

The Twenty -Sixth Work Week Of The St. Peter Church Expansion Project

This week the Carpenters fished up most of the rough carpenter work in the main church. The Insulators worked on finishing up rapping heating sheet metal in the lower church. The stone masons worked on the masonry worked on fishing up with the cream city brick on the east side of the outer church wall. On the front main entrance, they continue to work on belt-line blocks and start on cream city blocks. The electricians continue to run wires and electrical outlets in the lower and upper church. The main Altar restoration project continue to be work on.

In the lower church main church entry way pipe fitters people continue to work on installing the sprinkler system. . The heating and air conditioning people continue working on sheet metal work. The dry-wallers continue to polish, taping, and placing wallboard in the low and upper church.

Видео The Twenty Sixth Work Week of St Peter Church Expansion Project August 22 thru 26, 2016 канала Richard Zautcke
Показать
Комментарии отсутствуют
Введите заголовок:

Введите адрес ссылки:

Введите адрес видео с YouTube:

Зарегистрируйтесь или войдите с
Информация о видео
27 августа 2016 г. 2:40:20
00:12:37
Яндекс.Метрика